Carrier 42D, 42C, 42S, 42V specifications Attach unit risers

Models: 42V 42D 42S 42C

1 72
Download 72 pages 52.3 Kb
Page 42
Image 42
7.Attach unit risers:

h.After all drywalling and painting is complete, install thermostats, supply air grilles and return air panels.

7.Attach unit risers:

Manual background CAUTION

Toxic residues and loose particles resulting from manufac- turing and field piping techniques such as joint compounds, soldering flux, and metal shavings may be present in the unit and the piping system. Special consideration must be given to system cleanliness when connecting to solar, domestic or portable water systems. Failure to heed this warning could result in equipment damage.

NOTE: The supply and return connections are marked on the coil stub-outs and the valve package with an “S” meaning supply or inlet and “R” meaning return or outlet indicating flow direction to and from the coil. Blue letters mark the chilled water connections and red letters mark the hot water connections.

a.Each riser has a 3-in. swaged portion at top and sufficient extension at bottom for an inserted length of approximately 2-in. This unit-to-unit joint is NOT intended for full bottoming in the joint, but allows for variations in floor-to-floor dimensions and for correct riser positioning.

If job requires that unit risers be supplemented with between-the-floor extensions pieces may be field-supplied or factory-supplied. If factory- supplied, insulation is also provided.

b.Level unit to ensure proper coil operation and condensate drainage. Proper riser installation and vertical positioning in the unit provides for a unit piping run-out to the service valves which are cen- tered in the access slots and level or sloping down slightly away from the riser. This prevents con- densation from running back to the riser and pos- sible damage from dripping at the bottom of a riser column. After units are positioned and riser centered in pipe chase, make unit plumb in two directions, using unit frame as a reference.

c.Anchor unit to building. Use bolts or lag screws through holes provided in unit frame.

d.After all units in a stack are anchored, make unit- to-unit riser joints. First, center each coil-to-riser line within the expansion slot in the unit back panel. Each riser joint must be in vertical alignment with at least 1-in. penetration into the swaged joint. This condition is met if floor-to- floor dimension is as specified and coil-to-riser lines are properly centered. Wide variations in floor-to-floor dimensions may necessitate cutting off or extending individual risers. Such modifica- tions are the full responsibility of the installing contractor.

e.Before making the riser joints, the riser insulation must be pulled back away from the joint and pro- tected from heat during the soldering process. Sol- der riser joints with phos-copper, silfos, or other high temperature alloy. The riser joint filler mate- rial must be selected to withstand the total operat- ing pressure (both static and pumping head) to which the system will be subjected. Soft solder (50-50, 60-40, or 85-15) or other low temperature lead alloy is not suitable for this application.

IMPORTANT: Chilled water and hot water risers should never be piped to drain down into the condensate riser. Extensive water damage can occur due to drain over- flow. Drain chilled and hot water risers to a remote loca- tion away from the unit such as sink, room and floor drains.

8.Anchor risers as required:

a.Do not fasten risers rigidly within each unit. Risers must be free to move within pipe chase in response to normal vertical expansion and contraction.

b.Built in risers must be anchored at some point to building structure. Unit design accommodates up to 11/2-in. expansion and contraction in riser assemblies when positioned properly at the job site. Risers must be anchored to the building struc- ture to limit expansion and contraction movement to a maximum of 11/2-inches. Riser anchoring and expansion compensation is not included in the fac- tory-supplied unit and must be provided.

9.Test the system for leaks after the connections are com- pleted. When testing with air or some other gas, it might be necessary to tighten stem packing nuts on some valves to maintain air pressure in the riser. Pressure testing risers with water should be done with the unit service valves closed to prevent flushing debris into the unit valve pack- ages. This will also allow risers to be drained down after testing in the winter to avoid freeze-up problems.

10.After system integrity has been established, pull the riser insulation back into place over the joint and glue or seal to prevent sweating and heat loss or gain. Internal chilled water piping and valves are located over the drain pan and need not be insulated.

11.If required, fireproof were necessary. Any fireproofing re- quirements where risers or piping penetrate floors or walls are the responsibility of the installer. This work should be done only after all pressure testing is complet- ed. The fireproofing method used must accommodate pipe expansion and contraction and the piping must be protected from abrasion and chemical attack. The pipe in- sulation also must be maintained to prevent sweating and must be protected from wear or erosion at the joint be- tween the insulation and the fireproofing material.

Step 2 — Make Piping Connections — Access to piping is available through the access panels at the side of the units or front of the unit. Qualified personnel in accordance with local and national codes must perform all piping connec- tions. Refer to Tables 1-4 for piping connections.

NOTE: It is important to have a common understanding of which side of the unit is the right hand side and which is the left hand side.

When facing the supply air outlet from the front of the unit (air blowing in your face), your right hand will be on the right side of the unit and your left hand will be on the left side of the unit. See Fig. 40. Refer to Fig. 41 and 42 for typical piping connections.

The supply and return piping connections of the factory- provided valve package are either swaged for field brazing (standard) or union fitted (optional) for field connection to the coil.

42

Page 42
Image 42
Carrier 42D, 42C, 42S, 42V specifications Attach unit risers