I.Project Information
Job Name _______________________________________________________________________
Address ________________________________________________________________________
City ______________________________________________State __________ Zip __________
Installing Contractor _______________________________________________________________
Sales Office _____________________________________________________________________
INSPECTION, INSTALLATION, AND START-UP CHECKLIST
ITEM | COMPLETE | ||
Receiving & Inspection |
| ||
1. | Unit received undamaged |
| |
2. | Unit received complete as ordered |
| |
3. | “Furnish only” parts accounted for |
| |
4. | Unit arrangement/hand correct |
| |
5. | Unit structural support complete and correct |
| |
Handling & Installation |
| ||
6. | Mounting grommets/isolators used |
| |
7. | Unit mounted level and square |
| |
8. | Proper access provided for unit and accessories |
| |
9. | Proper electrical service provided |
| |
10. | Proper overcurrent protection provided |
| |
11. | Proper service switch/disconnect provided |
| |
12. | Proper chilled water line size to unit |
| |
13. | Proper hot water line size to unit |
| |
14. | Proper refrigerant line sizes to unit |
| |
15. | Proper steam line sizes to unit |
| |
16. | Proper steam condensate trap on return line |
| |
17. | Proper steam supply pressure to unit (10 psi max) |
| |
18. | All service to unit in code compliance |
| |
19. | All shipping screws and braces removed |
| |
20. | Unit protected from direct & foreign matter |
| |
Cooling/Heating Connections |
| ||
21. | Protect valve package components from heat |
| |
22. | Mount valve packages |
| |
23. | Connect field piping to unit |
| |
24. | Pressure test all piping for leaks |
| |
25. | Install drain line and traps as required |
| |
26. | Insulate all piping as required |
| |
27. | Install drip lip under piping as required |
| |
Ductwork Connections |
| ||
28. | Install ductwork, fittings, and grilles as required |
| |
29. | Flexible duct connections at unit |
| |
30. | Proper supply and return grille type and size used |
| |
31. | Control outside air for freeze protection |
| |
32. | Insulate all ductwork as required |
|
ITEM | COMPLETE | |
Electrical Connections |
| |
33. | Refer to unit wiring diagram |
|
34. | Connection incoming power service(s) |
|
35. | Install and connection “furnish only” parts |
|
36. | All field wiring in code compliance |
|
Unit |
| |
37. | General visual unit and system inspection |
|
38. | Check for proper fan rotation |
|
39. | Record electrical supply voltage |
|
40. | Record ambient temperatures |
|
41. | Check all wiring for secure connections |
|
42. | Close all unit isolation valves |
|
43. | Flush water systems |
|
44. | Fill systems with water/refrigerant |
|
45. | Vent water systems as required |
|
46. | All ductwork and grilles in place |
|
47. | All unit panels and filters in place |
|
48. | Start fans, pumps, chillers, etc. |
|
49. | Check for overload condition of all units |
|
50. | Check all ductwork and units for air leaks |
|
51. | Balance air systems as required |
|
52. | Record all final settings for future use |
|
53. | Check piping and ductwork for vibration |
|
54. | Check all dampers for proper operation |
|
55. | Verify proper cooling operation |
|
56. | Verify proper heating operation |
|
57. | Reinstall all covers and access panels |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|