Maintenance Bypass Cabinet
7.Connect the system input cables between the Maintenance Bypass Cabinet 'UPS Input' Busbars
8.Connect the system outnput cables between the Maintenance Bypass Cabinet 'UPS Output' Busbars
9.Connect supplied control wire to X3 on the Parallel (M3) board (see Figure 20).
! WARNING
The control wire must be installed to ensure proper operation of the system and fully protect the load when switching between bypass cabinet and UPS.
Figure 20 | Maintenance bypass control wire location |
|
|
|
|
|
| X2 | P2 | A M T :X | 485+ |
| Terminal Block Location |
| |||
|
|
|
| ||
|
|
|
|
| |
|
|
|
| X3 |
|
|
|
|
| DBS |
|
| 1 | X2 | P1 |
|
|
NOTE
For startup procedure, see the UPS operations and maintenance manual,