Hoshizaki KM-201BWH, KM-260BAH, KM-201BAH bREFRIGERANT RECOVERY, cEVACUATION AND RECHARGE R-404A

Models: KM-201BWH KM-260BWH KM-201BAH KM-260BAH

1 81
Download 81 pages 49.56 Kb
Page 51
Image 51
[b]REFRIGERANT RECOVERY

3.Do not replace the drier until after all other repair or replacement has been made. Install the new drier with the arrow on the drier in the direction of the refrigerant flow.

4.When brazing, protect the drier by using a wet cloth to prevent the drier from overheating. Do not allow the drier to exceed 250°F (121°C).

[b]REFRIGERANT RECOVERY

The icemaker unit is provided with refrigerant access valves. Using proper refrigerant practices, recover the refrigerant from the access valves and store it in an approved container. Do not discharge the refrigerant into the atmosphere.

[c]EVACUATION AND RECHARGE (R-404A)

1)Attach a vacuum pump to the system. Be sure to connect the charging hoses to both high and low-side access valves.

IMPORTANT

The vacuum level and vacuum pump may be the same as those for current refrigerants. However, the rubber hose and gauge manifold to be used for evacuation and refrigerant charge should be exclusively for POE oils.

2)Turn on the vacuum pump. Open the gauge manifold valves. Never allow the oil in the vacuum pump to flow backwards.

3)Allow the vacuum pump to pull down to a 29.9” Hg vacuum. Evacuating period depends on pump capacity.

4)Close the low-side valve and high-side valve on the gauge manifold.

5)Disconnect the gauge manifold hose from the vacuum pump and attach it to a refrigerant service cylinder. Remember to loosen the connection and purge the air from the hose. For air-cooled and water-cooled models, see the nameplate for the required refrigerant charge. For remote air-cooled model, see the rating label inside the icemaker. Hoshizaki recommends only virgin refrigerant or reclaimed refrigerant which meets ARI Standard 700 (latest edition) be used.

6)A liquid charge is recommended for charging an R-404A system. Invert the service cylinder and place it on scales. Open the high-side valve on the gauge manifold.

7)Allow the system to charge with liquid until the proper charge weight is met.

46

Page 51
Image 51
Hoshizaki KM-201BWH, KM-260BAH, KM-201BAH, KM-260BWH service manual bREFRIGERANT RECOVERY, cEVACUATION AND RECHARGE R-404A