14 | Installation (for qualified installers only) |
Nailing Brackets
There are four nailing brackets on the front of the fireplace. Follow the directions below to prepare the nailing brackets. Once in place, nail or screw the nailing brackets to the framing.
NOTE: Additional nailing brackets are provided along
the base of the fireplace. Use these brackets if not using the front brackets.
1/2” Drywall
For installations using
1/2” facing fold the larger
tab out 90° (use a
screwdriver if necessary).
5/8” Drywall
For installations using 5/8” drywall fold the shorter tab out 90° (use a screwdriver if necessary).
WARNING: Make sure the
fireplace is square and
plumb when placed in the framing. Measured
TOP VIEW
Framing
Nailing Bracket
Fireplace
Drywall
TOP VIEW
Framing
Nailing Bracket
Fireplace
Drywall
Travis Industries | 4070201 |