PEAK POWER RATINGS

The amount of power the E-AC Drive requires from your AC power source depends upon the motor you use, whether you wire the motor in series or parallel, and upon your specific application. The next table shows peak power requirements. Power required for your application may be less.

Motor Type

Current

Cabinet

Peak Motor

Peak Shaft

Peak Total

Volt-Amp

 

(Amps)

Loss (W)

Loss (W)

Power (W)

Power (W)

Rating (VA)

OS2HBS

1.70

22.0

22

39

83

151

OS2HBP

3.39

32.0

76

82

190

314

OS21BS

1.82

24.0

30

65

119

205

OS21BP

3.50

55.0

86

129

270

432

OS22BS

2.38

18.0

41

87

146

247

OS22BP

3.50

29.0

93

161

283

451

VS12BS

1.02

17.0

29

32

78

141

VS12BP

2.04

24.0

87

33

144

266

VS13BS

1.02

18.0

25

38

81

147

VS13BP

2.04

39.0

93

32

164

280

VS21BS

2.27

18.0

60

100

178

300

VS21BP

3.50

37.0

105

137

279

438

VS22BS

2.04

13.0

46

93

152

258

VS22BP

3.50

36.0

95

149

280

452

VS23BS

2.04

14.0

39

113

166

281

VS23BP

3.50

24.0

99

202

325

531

VS31BS

3.05

19.0

45

135

199

339

VS32BS

3.16

22.0

57

121

200

334

S: Series Configuration P: Parallel Configuration

9 –TEST THE INSTALLATION

System installation should be complete at this point. Perform the test procedure below to verify that your system is functioning properly.

In the test procedure, you will command single revolution moves in the clockwise and counterclockwise direction. If your mechanics do not permit such moves, choose a move that allows you to easily verify correct system response.

TEST PROCEDURE

1.Apply 120VAC power. The green LED labeled PWR should illuminate.

2.Command a slow move of one revolution in the clockwise direction. Verify that the motor turns as commanded.

3.Command a slow move of one revolution in the counterclockwise direction. Verify that the motor turns as commanded.

4.Test the shutdown input. With the motor stopped, activate the input. The motor will have no torque when shutdown is activated. You should be able to turn the motor manually (if your mechanics permit).

Successful completion of this procedure will verify that your controller and motor are correctly connected to the E-AC Drive, and that the drive is functioning properly.

If the test is unsuccessful, proceed to Chapter 3 Troubleshooting for problem identification and solution procedures.

30

E-AC Drive Hardware Installation Guide

Chapter 2 – Installation

Page 30
Image 30
Parker Hannifin 88-020292-01 A manual Test the Installation, Peak Power Ratings, Test Procedure