Base construction and installation of the indoor · outdoor unit
Installing indoor unit
1Open the air inlet grille in the front and unscrew
4 bolts on the bottom of the product. | 4 bolts |
|
2 Remove the wooden palette used for product transport.
3 Install the product on an even floor.
INSTALLATION PARTS
Installing Outdoor unit
WARNING
•Make sure to remove the wooden pallet before installing the outdoor unit. If you do not remove the wooden pallet, there is risk of fire during welding the pipes. If the outdoor unit is installed with wooden pallet on, and it was used for long period time, wooden palette may break and cause electrical hazard or high pressure may damage the pipes.
1Install the outdoor unit 150mm higher than the base ground and install the drain hole to connect the pipe to the drainage.
2When the front fan of an outdoor unit is installed in a place where the average snowfall is more than 150mm, the discharge duct should be attached to the outdoor unit.
3The concrete foundation should be 1.5 times larger than bottom of the outdoor unit.
4It is necessary to install wire mesh or steel bar when outdoor units are installed on a soft foundation.
5When installing multiple outdoor units at the same place, install the H beam on the base ground. (When installing a number of outdoor units, you can install it on the base ground.)
6Install the H beam(150mm x 150mm x t10 : basic specification) or vibration absorption frame to jut out from the base ground.
7After installing the H beam, apply corrosion protection.