INSTALLATION PARTS

Check lists after completing the installation

After completing the installation, you must check the following.

 

 

• Have you checked the external surface and the internal part of the

 

 

indoor unit?

 

Indoor

• Is the place well-ventilated and ensures space for service?

 

unit

• Have you checked if the center of the indoor unit is ensured and it is

 

 

installed horizontally in level?

Installation

 

• Have you connected refrigeration pipes properly?

 

• Have you checked the external surface and the internal part of the

 

 

 

 

outdoor unit?

 

Outdoor

• Is there any possibility of short circuit due to the heat of an outdoor

 

unit

unit?

 

 

• Is the place well-ventilated and ensures space for service?

 

 

• Is the outdoor unit fixed securely?

 

 

• Have you checked for any gas leakage?

 

 

• Are the length and the height difference between the refrigerant pipes

Refrigerant pipe

within the allowable range?

• Have you properly insulated pipes?

work

• Is the quantity of the additional refrigerant correctly weighed in?

 

 

 

 

• You must record the amount of additional refrigerant charging on the

 

 

service record label placed outside the outdoor unit.

Installing the

• Have you completed the drain test?

drain pipe

• Is the drainpipe properly insulated?

 

 

 

 

 

• Have you checked for interference between the power and the

 

 

communication cable?

Wiring work

• Have you performed the earthing work 3 to the outdoor unit?

• Is the length of the wire within allowable range?

 

 

 

 

• Is the wiring route correct?

 

 

• Have you used verified power supply cable and the communication cable?

Option

• Check whether the vibration-resistance frame is correctly installed if

there is a possible vibration of the outdoor unit.

 

 