Caution – The shipping cradle must be attached when the server is lifted. Failure to do so will result in major damage to the server.

2.Insert the forks of the lifting device fully through the shipping cradle opening (FIGURE 1-10).

FIGURE 1-10Inserting the Lifting Device Into the Shipping Cradle

3.Lift the server off the wooden shipping pallet and remove the pallet.

4.Extend the outer rails from the cabinet and latch them in the extended position.

5.Lift the server until it is level with the outer rails on the cabinet.

6.Carefully move the lifting device forward until the rails on the server are fully engaged with the outer rails on the cabinet (FIGURE 1-11).

The latches on each side must click out, locking the rails.

18 Netra 1290 Server Installation Guide • May 2006

Page 30
Image 30
Sun Microsystems 1290 manual Latches on each side must click out, locking the rails