Installation

Installation

3 Installation

3.1.1 Tools Required

In addition to the standard tool kit, the tools in Table 3.1 are recommended for installation of the option panel.

3.1.2 Drive Fuses

TOOLS

Spreader bar capable of lifting up to 750 lbs.

Max diameter 0.5 in.

Forklift, crane, hoist or other lifting device capable of handling up to 750 lbs. (Qualified device operator available for operating the equipment.)

Metric Socket Set: 7 - 19mm

Socket Extensions: 4, 6, and 12 inch

Torx driver set: T10 - T40

Torque wrench: 6 - 375 lbs-in

Allen Wrenches:1/8, 3/16, 1/4, & 5/16 inches

Metric or English wrenches: 7 - 19mm

Table 3.1 Tools Required

To maintain UL, the drive fuses should be replaced only with the fuses specified in , , , and . If an alternate drive fuse is desired please consult the factory. See the specifications label inside the cover of the unit for acceptable replacement drive fuses. A sample of this data can be seen in Table 3.6

208 V AC

HP (KW)

UL Motor

Panel (TR200) Non Bypass

Main Fuse (TR200)

Drive Fuse (TR200)

Transformer Fuse (TR200)

Current

& Bypass

Bussman

Bussman

Bussman

 

 

7.5

(5.5)

24,2

 

LPJ-40-SP

JJN-50

 

10 (7.5)

30,8

P2

LPJ-50-SP

JJN-50

 

15

(11)

46,2

 

LPJ-70-SP

JJN-60

 

 

 

 

 

 

 

 

20

(15)

59,4

P3

LPJ-90-SP

JJN-80

 

 

 

 

 

 

 

 

25 (18.5)

74,8

P3 - Non Bypass P4 -

LPJ-125-SP

JJN-125

 

Bypass

 

 

 

 

 

 

 

 

 

 

 

 

 

 

30

(22)

88

P4

LPJ-150-SP

JJN-125

 

 

 

 

 

 

 

40

(30)

114

LPJ-175-SP

JJN-150

 

 

 

 

 

 

 

 

 

 

50

(37)

143

P5

LPJ-250-SP

JJN-200

FNQ-R-1.25

 

 

 

 

 

 

60

(45)

169

LPJ-250-SP

JJN-250

FNQ-R-1.25

 

 

 

 

 

 

 

 

Table

3.2 Drive Fuses 208 V

 

 

 

 

BAS-SVX49A-EN

3-1

Page 15
Image 15
Trane Vertical Bypass/Non Bypass Panel, TR200 specifications Installation, Drive Fuses, 1 Tools Required, V Ac