8.Remove the runner from which all lag bolts have been removed (refer to Figure 6).

Figure 6 Remove runner from pallet

Slide this runner away

from the Liebert XDP

9.Using the pallet jacks, raise the secured unit to the highest point that the piano jacks will allow. Once the unit has been raised, slide the remainder of the pallet from under the Liebert XDP (see Figure 7). Lower the Liebert XDP so that its base is approximately 1" (25.4mm) off the ground.

Figure 7 Sliding pallet from under Liebert XDP

Slide the remaining part of the pallet from under the Liebert XDP so the unit may be moved on the piano jacks.

1.3.3Removing Piano Jacks

Once the unit has been moved to the installation location, Emerson Network Power recommends the following method to remove the piano jacks:

1.Lower the unit as far as the piano jacks will allow.

2.Undo all strapping holding the piano jacks to the unit.

3.Remove all cushioning material used to protect the unit from the straps and the piano jacks.

4.Use a pry bar or other lever to lift one side of the Liebert XDP enough to allow removal of the piano jack.

5.Repeat Step 4 to remove the piano jack on the opposite side.

6.Remove the plastic bag.

4

Image 10
Contents Liebert XDP Fluorinated Greenhouse Gas Requirements-European Union General Safety GuidelinesExample XDP160A Pumping Place holder Revision Unit Redundancy Level LiebertTable of Contents Alarm Descriptions and Solutions SpecificationsFigures Page Product Description General Product InformationEquipment Inspection Product/System DescriptionHandling With Skid Equipment HandlingRemoval from Skid Removing pallet boards for piano jack insertion Liebert XDP strapped to piano jackRemoving Piano Jacks Slide this runner away From the Liebert XDPMechanical Considerations Liebert XDP dimensionsPositioning the Liebert XDP Unit piping outlet connection sizes, inches, OD Cu Model Pipe Connection Point 50/60 HzConnecting High-Voltage Cables Electrical Information High Voltage ConnectionsElectrical enclosure knockout locations for field wiring Extra Low Voltage ELV Connections High voltage connections-50HzField Connections-All Units Field Connections-Optional for All UnitsPiping European Union Fluorinated Greenhouse Gas RequirementsConnection Sizes Recommended Pipe SizeBypass Flow Controller Piping Installation MethodLiebert XDP Interconnection with Liebert XD Cooling Modules Bypass flow controllers for a Liebert XDP-based systemBypass flow controller details, dimensions Bypass flow controller arrangementPiping Mains Piping Installation MethodPiping Details-Shut-Off/Isolation Valves Evacuation and Leak CheckChecklist for Proper Installation Liebert XDP pump light indicator-208V and 400V units Checklist for Liebert XDP StartupIndicator Lights Description Green Red Filling the Pumped Circuit-R-134a System R-134a liquid levelReturn Line Diameter 5/8 System refrigerant charge for the supply and return mainsReturn Line Diameter Worksheet to calculate refrigerant charge Calculating Refrigerant Charge-ExampleCalculating refrigerant charge-example Total 293Display Feature OverviewMicroprocessor Control User interface keypad functionsControls Feature OverviewViewing or Changing Settings Main MenuSetpoints Active AlarmsAlarm History MIN Temp SPDegrees Setup OperationRestart Time Delay Pump Start TDPump OFF TD Liebert XDP DIP switches and factory settingsPump Wait TD Lead PumpChange Password-SETPT Password Password Security-SETPT Password and Service PasswordValve Time Alarm Time Delay Change Password-SERVICE PasswordAlarm Enable COM Alarm EnableDiagnostics Custom AlarmsCustom Text Alarm Descriptions Alarm Descriptions and SolutionsAlter Alarm Settings Red and Green Lamp IndicatorsEnable or Disable Alarms System Shutdown Causes Troubleshooting Troubleshooting the XDPMaintenance Fluorinated Greenhouse Gas RequirementsSpecifications Liebert XDP160 specificationsTi n Ne tIti That