Liebert XDP user manual Checklist for Proper Installation

Page 21

Piping

2.6Checklist for Proper Installation

___ 1. Unpack and check received material.

___ 2. Position the Liebert XDP and secure it to the floor.

___ 3. Wire high voltage connections.

___ 4. Wire low voltage connections.

___ 5. Connect the building chilled water piping to the Liebert XDP.

___ 6. Connect the Liebert XD cooling module piping to the Liebert XDP.

___ 7. Check the system for leaks.

___ 8. Hold a vacuum on the system.

___ 9. Charge the system with refrigerant.

___ 10. Make sure that all piping has proper insulation.

15

Image 21
Contents Liebert XDP Example XDP160A General Safety GuidelinesFluorinated Greenhouse Gas Requirements-European Union Pumping Place holder Revision Unit Redundancy Level LiebertTable of Contents Specifications Alarm Descriptions and SolutionsFigures Page Equipment Inspection General Product InformationProduct Description Product/System DescriptionEquipment Handling Handling With SkidRemoval from Skid Liebert XDP strapped to piano jack Removing pallet boards for piano jack insertionSlide this runner away From the Liebert XDP Removing Piano JacksLiebert XDP dimensions Mechanical ConsiderationsPositioning the Liebert XDP Model Pipe Connection Point 50/60 Hz Unit piping outlet connection sizes, inches, OD CuElectrical Information High Voltage Connections Connecting High-Voltage CablesElectrical enclosure knockout locations for field wiring High voltage connections-50Hz Extra Low Voltage ELV ConnectionsField Connections-Optional for All Units Field Connections-All UnitsConnection Sizes European Union Fluorinated Greenhouse Gas RequirementsPiping Recommended Pipe SizeLiebert XDP Interconnection with Liebert XD Cooling Modules Piping Installation MethodBypass Flow Controller Bypass flow controllers for a Liebert XDP-based systemBypass flow controller arrangement Bypass flow controller details, dimensionsPiping Details-Shut-Off/Isolation Valves Piping Installation MethodPiping Mains Evacuation and Leak CheckChecklist for Proper Installation Checklist for Liebert XDP Startup Liebert XDP pump light indicator-208V and 400V unitsIndicator Lights Description Green Red System R-134a liquid level Filling the Pumped Circuit-R-134aSystem refrigerant charge for the supply and return mains Return Line Diameter 5/8Return Line Diameter Calculating refrigerant charge-example Calculating Refrigerant Charge-ExampleWorksheet to calculate refrigerant charge Total 293Microprocessor Control Feature OverviewDisplay User interface keypad functionsViewing or Changing Settings Feature OverviewControls Main MenuAlarm History Active AlarmsSetpoints MIN Temp SPRestart Time Delay Setup OperationDegrees Pump Start TDPump Wait TD Liebert XDP DIP switches and factory settingsPump OFF TD Lead PumpPassword Security-SETPT Password and Service Password Change Password-SETPT PasswordValve Time Alarm Enable Change Password-SERVICE PasswordAlarm Time Delay COM Alarm EnableCustom Alarms DiagnosticsCustom Text Alarm Descriptions and Solutions Alarm DescriptionsRed and Green Lamp Indicators Alter Alarm SettingsEnable or Disable Alarms System Shutdown Causes Troubleshooting the XDP TroubleshootingFluorinated Greenhouse Gas Requirements MaintenanceLiebert XDP160 specifications SpecificationsIti Ne tTi n That