GE 300, 225 manual Electrical Wiring, Separate input Rectifier & Bypass recommended

Page 17

g

GE

3.7ELECTRICAL WIRING

UPS installation and connection must be performed by qualified service personnel only.

It is the responsibility of the installation technician to ensure that all local and national electric codes are adhered to.

3.7.1Utility input connection

Ensure that the AC and DC external isolators are OFF and locked out to prevent their inadvertent operation.

Do not apply power to the equipment prior to the commissioning by a qualified service engineer.

Before any other input connection, connect and check the grounding wire.

The UPS has available input terminations for the Rectifier and Bypass.

The unit may be powered from a common input source or separate input sources if desired.

Separate input Rectifier & Bypass (recommended)

The Bypass and Rectifier Inputs are to be powered from different Utility supplies (F1 and F2 inputs).

In this case, when the Rectifier Input Fuses are opened, the Bypass and the Manual Bypass are supplied by the other source.

In this case, remove the interconnection links BR1, BR2 and BR3 on the input terminals or bus bars. See Fig. 3.8.3-2.

Common input Rectifier & Bypass

The same power source is to be used for both Bypass Supply and Rectifier Input (input F3).

Bear in mind that when the Utility Fuses are opened there is a supply failure to the Rectifier as well as to the Bypass and Manual Bypass.

In this case, the interconnection links BR1, BR2 and BR3 on the input terminals or bus bars must remain connected. See Fig. 3.8.3-2.

Separate input Rectifier & Bypass (recommended)

 

Common input Rectifier & Bypass

 

Fig. 3.7.1-1 Separate input Rectifier & Bypass

Fig. 3.7.1-2 Common input Rectifier & Bypass

1

=

Rectifier

3

=

Automatic Bypass

6

=

Load

7 = Battery

2

=

Inverter

4

=

Manual Bypass

5

=

Utility input

 

OPM_SGS_ISG_M22_M30_0US_V011.doc

17/38

Installation Guide SG Series 225 & 300 kVA

Image 17
Contents SG Series Systems Copyright 2003 by GE Industrial SystemsStart UP and Commissioning Dear CustomerPreface Table of contents Battery InstallationGeneral StorageSafety instructions when working with battery Safety warnings Safety symbols and warningsRisk of electric shock PE Earth GND Ground Protective Grounding TerminalLayout SG Series 225 and 300 KVA LayoutWeight SG Series 225 and 300 kVA Dimensions and weightTransport Forklift Crane Transport UPS only in upright positionStorage of the UPS Storage of BatteryDelivery Check -26A of the NEC code for specific requirements Place of InstallationPositioning of the UPS SG Series Fixing of the UPS cabinet on the floor Openings for input and output cable connections1-5 RPA system disposition Battery locationCFM Ventilation and CoolingPacking material recycling Take care not to damage the UPS when moving by forkliftUnpacking Common input Rectifier & Bypass Electrical WiringSeparate input Rectifier & Bypass recommended Neutral current could be greater than the phase currents Input/output over current protection and wire sizingPhase, 4 wire plus Ground Phase, 3 wire plus GroundWire positive and negative plus Ground See .7.1-1Copper Wire Size Range Wiring Connection1-1 Access to the input / output connections Output Load Power connection with common input utilityCommon Input Rectifier / Bypass Cable section for this connection shall be not less then AWG L1-1 Rectifier Phase a L1-2 Power connection separate input utilityL2-1 Rectifier Phase B L2-2 L3-1 Rectifier Phase C L3-2BR1 Battery Battery connectionPositive pole of the Battery Do not insert the Battery Fuses before the commissioningManual Bypass, serious damage to the Load could result Setup for SG Series when functioning as frequency converter1 RPA Parallel System Power Wiring of Parallel UnitsParallel Control BUS Connection UPSIntermediate units Terminal unitsControl BUS Cable Location Access to the control bus connectionControl bus cables connection Interface IM0048 going to P1311-3 Control Bus cable routing and connection Control bus cables routingCustomer Interface Customer Interface18, 19 Or J2 20, 21 NO, C, NC Acoustic Alarm 15, 16 Or J2 17, 18 NO, C, NC General AlarmOutput potential free contacts Or J2 / 1, 2 NO, C, NC Utility FailureGND JP3 EPO Emergency Power Off Input contact38/38