GE 300, 225 manual Battery connection, Positive pole of the Battery

Page 27

g

GE

3.8.4 Battery connection

ttery_01US

 

ba

 

connection

 

-300_UPS

 

SGS_225

 

Q1

Q2

 

BATTERY

_ PE

+

Fig. 3.8.4-1 Power connections Battery

Battery

+

Positive pole of the Battery

Negative pole of the Battery

Do not insert the Battery Fuses before the commissioning.

Battery Cable Terminations are to the Positive and Negative Terminals as shown above. Connect wire to the Lugs using appropriate tools and appropriate torque.

Torque specification for Input/Output and DC power connections on Bus Bars: See section 3.8.1.

OPM_SGS_ISG_M22_M30_0US_V011.doc

27/38

Installation Guide SG Series 225 & 300 kVA

Image 27
Contents SG Series Systems Copyright 2003 by GE Industrial SystemsStart UP and Commissioning Dear CustomerPreface Table of contents Storage InstallationBattery GeneralSafety instructions when working with battery Protective Grounding Terminal Safety symbols and warningsSafety warnings Risk of electric shock PE Earth GND GroundLayout SG Series 225 and 300 KVA LayoutTransport UPS only in upright position Dimensions and weightWeight SG Series 225 and 300 kVA Transport Forklift CraneStorage of Battery DeliveryStorage of the UPS Place of Installation Positioning of the UPS SG SeriesCheck -26A of the NEC code for specific requirements Fixing of the UPS cabinet on the floor Openings for input and output cable connections1-5 RPA system disposition Battery locationCFM Ventilation and CoolingTake care not to damage the UPS when moving by forklift UnpackingPacking material recycling Electrical Wiring Separate input Rectifier & Bypass recommendedCommon input Rectifier & Bypass Neutral current could be greater than the phase currents Input/output over current protection and wire sizingSee .7.1-1 Phase, 3 wire plus GroundPhase, 4 wire plus Ground Wire positive and negative plus GroundCopper Wire Size Range Wiring Connection1-1 Access to the input / output connections Power connection with common input utility Common Input Rectifier / BypassOutput Load Cable section for this connection shall be not less then AWG L3-1 Rectifier Phase C L3-2 Power connection separate input utilityL1-1 Rectifier Phase a L1-2 L2-1 Rectifier Phase B L2-2BR1 Do not insert the Battery Fuses before the commissioning Battery connectionBattery Positive pole of the BatteryManual Bypass, serious damage to the Load could result Setup for SG Series when functioning as frequency converter1 RPA Parallel System Power Wiring of Parallel UnitsParallel Control BUS Connection UPSIntermediate units Terminal unitsInterface IM0048 going to P13 Access to the control bus connectionControl BUS Cable Location Control bus cables connection11-3 Control Bus cable routing and connection Control bus cables routingCustomer Interface Customer InterfaceOr J2 / 1, 2 NO, C, NC Utility Failure 15, 16 Or J2 17, 18 NO, C, NC General Alarm18, 19 Or J2 20, 21 NO, C, NC Acoustic Alarm Output potential free contactsGND JP3 EPO Emergency Power Off Input contact38/38