This UPS is only designed to operate in a
In case of
1- Connection of a
Attention: With this configuration, load can only be connected phase- phase. Absolutely no load connection permitted to the Neutral of the output transformer.
In a RPA configuration with
Cable section for this connection shall be not less then AWG 1.
Fig. 3.8.3-2 3-wire kit for RPA Parallel System
2- Bypass transformer.
In this case the Neutral of wye secondary winding must be connected to the Neutral of the output transformer.
Contact your Service Centre, which will help you to find valuable solutions.
Notices for installation
Q2
Q1 | Q2 |
| |
| BR1 |
BR2
BR3
Fig. 3.8.3-3 AC bus bars BR1, BR2 and BR3
For separate Bypass and Rectifier input configuration AC bus bars BR1, BR2 and BR3 must be removed.