3.10 PARALLEL CONTROL BUS CONNECTION

In cases of parallel operation, the communication between the units takes place through the control bus cables.

Each parallel unit is equipped with an additional board “P13 RPA Board IM0006“ where the connectors J52 (A) and J62 (B) are located.

A short control cable provided with a ferrite ring core links the parallel board “P13 – RPA Board IM0048with the parallel bus socket on which must be connected the control bus cables JA and JB on PCB P34 – Bus Interface IM0048.

All the parallel units are connected to the same control bus.

This connection allows:

The microprocessors of each unit to communicate with each other.

The oscillators of each unit to be locked together.

The regulation loops to compare the output current of each unit in order to equally share the Load current.

For increased reliability, this connection is made with redundant cables.

In this way, communication is maintained between units in case one of the control cables should fail or be accidentally damaged or disconnected.

The standard length of the control bus cable between two parallel unit is 40 ft / 12 m.

Maximal overall length of bus connection, between the first and the last unit, should not be longer than 276 ft / 84 m.

Verify that control wiring is run in individual separate steel conduit.

Under no circumstance should the control bus cable connecting JA (1/2/3/4/5/6/7) and JB (1/2/3/4/5/6/7) be connected or disconnected after the system has been powered On.

UPS 1

 

UPS 2

 

UPS 3

 

JB1

JP1

JP2

JB1

JP1

JP2

JB2

JP1

JP2

 

 

IM 0048

JB2

 

IM 0048

JB3

IM 0048

-IM004801

 

 

 

 

 

 

 

 

RPA

JA1

JP4

 

JA1

JP4

 

JA2

JP4

SGT5000 100-150

 

JP3

 

JA2

JP3

 

JA3

JP3

 

 

 

 

JA1 + JB1

 

 

 

JA2 + JB2

 

JA3 + JB3

Next parallel

 

 

 

 

 

 

 

unit 4,5,6,7,8

 

 

 

Fig. 3.10-1 RPA System - Control bus connection

 

 

 

The shield of the control bus cable, connected on JA and JB must be connected to ground with the appropriate cable clamps fitted on parallel bus socket.

It is important to place the units in sequence of their assigned number.

A unit number from 1 to 8, is defined by the setting of parameters and displayed on the panel. This number is also marked inside and outside the packaging.

OPM_SGS_ISG_M22_M30_0US_V011.doc

30/38

Installation Guide SG Series 225 & 300 kVA

Image 30
Contents SG Series Copyright 2003 by GE Industrial Systems SystemsDear Customer Start UP and CommissioningPreface Table of contents General InstallationBattery StorageSafety instructions when working with battery Risk of electric shock PE Earth GND Ground Safety symbols and warningsSafety warnings Protective Grounding TerminalLayout Layout SG Series 225 and 300 KVATransport Forklift Crane Dimensions and weightWeight SG Series 225 and 300 kVA Transport UPS only in upright positionStorage of Battery DeliveryStorage of the UPS Place of Installation Positioning of the UPS SG SeriesCheck -26A of the NEC code for specific requirements Openings for input and output cable connections Fixing of the UPS cabinet on the floorBattery location 1-5 RPA system dispositionVentilation and Cooling CFMTake care not to damage the UPS when moving by forklift UnpackingPacking material recycling Electrical Wiring Separate input Rectifier & Bypass recommendedCommon input Rectifier & Bypass Input/output over current protection and wire sizing Neutral current could be greater than the phase currentsWire positive and negative plus Ground Phase, 3 wire plus GroundPhase, 4 wire plus Ground See .7.1-1Copper Wiring Connection Wire Size Range1-1 Access to the input / output connections Power connection with common input utility Common Input Rectifier / BypassOutput Load Cable section for this connection shall be not less then AWG L2-1 Rectifier Phase B L2-2 Power connection separate input utilityL1-1 Rectifier Phase a L1-2 L3-1 Rectifier Phase C L3-2BR1 Positive pole of the Battery Battery connectionBattery Do not insert the Battery Fuses before the commissioningSetup for SG Series when functioning as frequency converter Manual Bypass, serious damage to the Load could resultPower Wiring of Parallel Units 1 RPA Parallel SystemUPS Parallel Control BUS ConnectionTerminal units Intermediate unitsControl bus cables connection Access to the control bus connectionControl BUS Cable Location Interface IM0048 going to P13Control bus cables routing 11-3 Control Bus cable routing and connectionCustomer Interface Customer InterfaceOutput potential free contacts 15, 16 Or J2 17, 18 NO, C, NC General Alarm18, 19 Or J2 20, 21 NO, C, NC Acoustic Alarm Or J2 / 1, 2 NO, C, NC Utility FailureGND EPO Emergency Power Off Input contact JP338/38