Panel Configuration Select Range: [01..41] [02..42]

PDU Display Interface

Panel Configuration

Configure the branch metering settings for each breaker on the distribution panel. The panel position numbers on the screen correspond to the numbers on the distribution panel. (Odd numbers are on the left; even numbers are on the right.) Once you

have selected the correct range, configure the settings for each breaker in the range:

Pos: The panel positions in the selected range.

Breaker: Two configurable items:

The breaker rating, in amps.

The breaker tie indicator—define the number of panel positions tied (i.e., associated). You can associate positions with breakers, which enables you to view status about each breaker and receive alarm notification when any of a breaker’s poles are above or below the configured branch circuit limit. You can also tie together panel positions that are logically associated. For example, you can tie together panel positions for three separate breakers that are connected to the same PDU power cord and that feed power to the same equipment enclosure.

To configure the values on this screen:

1.From the first column, use the arrow keys to scroll up or down to the pole position you want to configure.

2.Press the ENTER key to move to the item you want to configure in the third column (the breaker rating or the breaker tie indicator).

3.Scroll again to select the value you want for the breaker rating or the breaker tie indicator. To associate one panel position with the next position in the list, choose the + character as the tie indicator immediately following the breaker rating. To indicate that the position is not tied to (associated with) the next panel position in the list, choose the ] character as the tie indicator immediately following the breaker rating. When you change the + or ] character that follows the breaker rating in one row, the + or [ character before the breaker rating in the next row also changes to indicate the changed association between the panel positions.

For example, this screen shows three, single-pole, 20A, tied

breakers occupying positions 08, 10, and 12 on the top right

 

Pos

Breaker

 

08

[

20A

+

 

distribution panel.

10

+

20A

+

12

+ 20A ]

 

Circuit breakers with ratings above 60A are considered sub-feeds. To configure a

 

subfeed circuit breaker, select a value above 60A. The interface will display “SUB”

Note

after the rating you have selected. Only the bottom 12 positions on the distribution

panel can be configured as sub-feeds.

 

26

80kW InfraStruXure PDU—Operation and Configuration

Image 34
Contents 80kW InfraStruXure PDU Page Audience How to find updates to this manualAbout This Manual Companion manualsPage Contents System Operation Specifications Product Information Cross-reference symbols used in this manual SafetySafety symbols used in this manual OverviewInstallation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPOEMI Overview InfraStruXure PDU ComponentsPDU front view exterior Front view interior  Wraparound Maintenance bypass Panel- Front view door openRear view interior PDU monitoring unit User connection plate  Page PDU Display Interface       Top-level menu screen Top-level status screensNavigating through screens Password-protected screens Power Factor Load-Meter ScreenVolt-Meter Screen Input Contacts Contacts ScreenOverview Open or ClosedPDU Display Interface How to connect contacts to the PDU monitoring unit Bypass Input Breakers ScreenMain Input Cross TieEntire Log Alarms ScreenNew Logged Items Clear LogLoading Limits Alarm SetupAlarm Beeper Voltage LimitsPDU Alarms Alarm Condition Explanation Message When Condition ClearedBranch Ckt Loading Panel ScreenBranch Ckt Limits Panel Configuration Distribution panelGlobal Panel Config System/Network Config ScreenSystem Password Date/TimeInput Config Electrical ConfigOutput Config Manufacturer Data Factory DefaultsFirmware Updates System IDHow to Transfer the UPS into Maintenance Bypass Operation System OperationSystem Operation System Operation How to Return from Maintenance Bypass Operation Confirm Yes, UPS Load on No, Abort Confirm Yes, UPS into Bypass No, Abort How to Ensure Total Power Off Set the UPS System Enable switch to the OFF positionSystem Operation How to Apply Power to the System PowerView RM Rev 000 English Please wait Top-Level Status Screen System Operation InfraStruXure Manager Communication ConfigurationInfraStruXure PDU Management Options Network management interfacesConfiguring the InfraStruXure Manager Connect the InfraStruXure PDU to the InfraStruXure ManagerConfiguration Overview Configuring the Network Management InterfaceConnect the InfraStruXure PDU to your network TCP/IP configuration methods Device IP Configuration WizardBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Use apc for the User Name and Password Local access to the control consoleRemote access to the control console Control console Use apc for both User Name and PasswordChoose Network from the Control Console menu Web interface Snmp FTP and SCP 80kW InfraStruXure PDU-Operation and Configuration Important Safety Instructions Customizing and Updating the PDUPDU Orderable Part List Power CablesCircuit Breakers 30A, 3-wire power cables Add a power cable to the PDU or RDP How to Add Circuit Breakers and Power CablesAdd a circuit breaker on the PDU Customizing and Updating the PDU How to Test the EPO Switch Testing the EPO wiring and switchesSafety warnings Customizing and Updating the PDU ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit Downloading firmware upgrades from a local computer How to Download Firmware UpgradesUpgrading the PDU monitor processor Xmodem Specifications 80kW InfraStruXure PDUPD80F6FK1-M PD80G6FK1-M PD80L6FK1-M PD80F6FK1-M PD80G6FK1-M PD80L6FK1-M Page InfraStruXure Standard Warranty Product InformationProduct Information APC Three-Phase Systems Life-Support PolicyHow to Obtain Service How to contact APCGeneral Changes AppendixChanges in This Manual Changes by page numberPage Index 80kW InfraStruXure PDU-Operation and Configuration UPS Page Page Page Page APC Worldwide Customer Support