How to Test the EPO Switch

Overview

APC offers an optional InfraStruXure EPO System (EPW9). Contact your APC sales representative, or visit the APC Web site (www.apc.com) for more information.

Note

After a certified electrician has connected an EPO switch to the PDU monitoring unit by way of the user connection plate, you can easily test the switch to make sure it is wired and working properly. The illustration below shows the EPO functions on the PDU monitoring unit.

EPO DIP switches configure the EPO input for the type of EPO switch that is connected—Normally Open (NO) or Normally Closed (NC).

 

 

T RIP

 

 

 

A RM E D

P

 

 

E

T E ST

 

 

 

N C

 

N O

 

 

When the EPO Arm/Test rocker is in the Test position, engaging the EPO switch will not cause the load to be powered off. When the rocker is in the Armed position, engaging the EPO switch will cause the PDU’s main input switch and the Symmetra PX UPS to be

switched OFF.

The EPO Armed LED is green when the rocker is in the Armed position. The led is dark

when the rocker is in the Test position.

The EPO Tripped LED is red when the EPO switch is engaged (the EPO button is pressed), regardless of the state of the EPO Arm/Test rocker.

Testing the EPO wiring and switches

1.Place the Arm/Test rocker switch in the Test position. The EPO state LEDs will be dark and the PDU display interface will show the following alarm (in addition to any other active alarms):

Active Alarm xxofxx

EPO Ready To Test

2.Engage the EPO switch. (If your switch is momentary, engage it with one person watching the EPO state LEDs, and another at the EPO switch.)

3.Observe the EPO LEDs. If the switch is wired and working properly, when the switch is engaged, both of the EPO state LEDs are red.

60

80kW InfraStruXure PDU—Operation and Configuration

Image 68
Contents 80kW InfraStruXure PDU Page How to find updates to this manual About This ManualAudience Companion manualsPage Contents System Operation Specifications Product Information Safety Safety symbols used in this manualCross-reference symbols used in this manual OverviewInstallation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPOEMI Overview InfraStruXure PDU ComponentsPDU front view exterior Front view interior  Wraparound Maintenance bypass Panel- Front view door openRear view interior PDU monitoring unit User connection plate  Page PDU Display Interface       Navigating through screens Top-level status screensTop-level menu screen Password-protected screens Power Factor Load-Meter ScreenVolt-Meter Screen Contacts Screen OverviewInput Contacts Open or ClosedPDU Display Interface How to connect contacts to the PDU monitoring unit Breakers Screen Main InputBypass Input Cross TieAlarms Screen New Logged ItemsEntire Log Clear LogAlarm Setup Alarm BeeperLoading Limits Voltage LimitsPDU Alarms Alarm Condition Explanation Message When Condition ClearedBranch Ckt Limits Panel ScreenBranch Ckt Loading Panel Configuration Distribution panelGlobal Panel Config Config Screen System PasswordSystem/Network Date/TimeOutput Config Electrical ConfigInput Config Factory Defaults Firmware UpdatesManufacturer Data System IDHow to Transfer the UPS into Maintenance Bypass Operation System OperationSystem Operation System Operation How to Return from Maintenance Bypass Operation Confirm Yes, UPS Load on No, Abort Confirm Yes, UPS into Bypass No, Abort How to Ensure Total Power Off Set the UPS System Enable switch to the OFF positionSystem Operation How to Apply Power to the System PowerView RM Rev 000 English Please wait Top-Level Status Screen System Operation Communication Configuration InfraStruXure PDU Management OptionsInfraStruXure Manager Network management interfacesConfiguring the InfraStruXure Manager Connect the InfraStruXure PDU to the InfraStruXure ManagerConnect the InfraStruXure PDU to your network Configuring the Network Management InterfaceConfiguration Overview TCP/IP configuration methods Device IP Configuration WizardBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleUse apc for the User Name and Password Choose Network from the Control Console menu Use apc for both User Name and PasswordControl console Web interface Snmp FTP and SCP 80kW InfraStruXure PDU-Operation and Configuration Important Safety Instructions Customizing and Updating the PDUCircuit Breakers Power CablesPDU Orderable Part List 30A, 3-wire power cables Add a circuit breaker on the PDU How to Add Circuit Breakers and Power CablesAdd a power cable to the PDU or RDP Customizing and Updating the PDU How to Test the EPO Switch Testing the EPO wiring and switchesSafety warnings Customizing and Updating the PDU ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit Upgrading the PDU monitor processor How to Download Firmware UpgradesDownloading firmware upgrades from a local computer Xmodem Specifications 80kW InfraStruXure PDUPD80F6FK1-M PD80G6FK1-M PD80L6FK1-M PD80F6FK1-M PD80G6FK1-M PD80L6FK1-M Page InfraStruXure Standard Warranty Product InformationProduct Information APC Three-Phase Systems Life-Support PolicyHow to Obtain Service How to contact APCAppendix Changes in This ManualGeneral Changes Changes by page numberPage Index 80kW InfraStruXure PDU-Operation and Configuration UPS Page Page Page Page APC Worldwide Customer Support