American Power Conversion PD80KF6FK1-M, PD80KG6FK1-M manual Customizing and Updating the PDU

Page 67

Customizing and Updating the PDU

4.At the front of the PDU, connect the power cord’s individual wires:

a.If you have branch current monitoring installed, route the phase conductor through a current sensor. If it is a three-phase cable, route the L1, L2, and L3 wires through a current sensor.

b.Connect the L1, L2, and L3 wires to the circuit breaker(s). The illustration below shows single pole circuit breakers; however, you can also connect three-pole breakers.

c.Connect the neutral wire to the closest open termination point on the Neutral Bar (N).

d.Connect the ground wire to the closest open termination point on the Ground Bar (G).

N

G

80kW InfraStruXure PDU—Operation and Configuration

59

Image 67
Contents 80kW InfraStruXure PDU Page Companion manuals How to find updates to this manualAbout This Manual AudiencePage Contents System Operation Specifications Product Information Overview SafetySafety symbols used in this manual Cross-reference symbols used in this manualMaintenance performed while the PDU is receiving input power Installation/MaintenanceEmergency Power Off EPO Total Power OffEMI InfraStruXure PDU Components OverviewPDU front view exterior Front view interior Front view door open  Wraparound Maintenance bypass Panel-Rear view interior PDU monitoring unit   User connection platePage        PDU Display InterfaceTop-level menu screen Top-level status screensNavigating through screens Password-protected screens Load-Meter Screen Power FactorVolt-Meter Screen Open or Closed Contacts ScreenOverview Input ContactsPDU Display Interface How to connect contacts to the PDU monitoring unit Cross Tie Breakers ScreenMain Input Bypass InputClear Log Alarms ScreenNew Logged Items Entire LogVoltage Limits Alarm SetupAlarm Beeper Loading LimitsAlarm Condition Explanation Message When Condition Cleared PDU AlarmsBranch Ckt Loading Panel ScreenBranch Ckt Limits Distribution panel Panel ConfigurationGlobal Panel Config Date/Time Config ScreenSystem Password System/NetworkInput Config Electrical ConfigOutput Config System ID Factory DefaultsFirmware Updates Manufacturer DataSystem Operation How to Transfer the UPS into Maintenance Bypass OperationSystem Operation System Operation How to Return from Maintenance Bypass Operation Confirm Yes, UPS Load on No, Abort Confirm Yes, UPS into Bypass No, Abort Set the UPS System Enable switch to the OFF position How to Ensure Total Power OffSystem Operation How to Apply Power to the System PowerView RM Rev 000 English Please wait Top-Level Status Screen System Operation Network management interfaces Communication ConfigurationInfraStruXure PDU Management Options InfraStruXure ManagerConnect the InfraStruXure PDU to the InfraStruXure Manager Configuring the InfraStruXure ManagerConfiguration Overview Configuring the Network Management InterfaceConnect the InfraStruXure PDU to your network Device IP Configuration Wizard TCP/IP configuration methodsBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Use apc for the User Name and Password Local access to the control consoleRemote access to the control console Control console Use apc for both User Name and PasswordChoose Network from the Control Console menu Web interface Snmp FTP and SCP 80kW InfraStruXure PDU-Operation and Configuration Customizing and Updating the PDU Important Safety InstructionsPDU Orderable Part List Power CablesCircuit Breakers 30A, 3-wire power cables Add a power cable to the PDU or RDP How to Add Circuit Breakers and Power CablesAdd a circuit breaker on the PDU Customizing and Updating the PDU Testing the EPO wiring and switches How to Test the EPO SwitchSafety warnings Customizing and Updating the PDU ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit Downloading firmware upgrades from a local computer How to Download Firmware UpgradesUpgrading the PDU monitor processor Xmodem 80kW InfraStruXure PDU SpecificationsPD80F6FK1-M PD80G6FK1-M PD80L6FK1-M PD80F6FK1-M PD80G6FK1-M PD80L6FK1-M Page Product Information InfraStruXure Standard WarrantyProduct Information Life-Support Policy APC Three-Phase SystemsHow to contact APC How to Obtain ServiceChanges by page number AppendixChanges in This Manual General ChangesPage Index 80kW InfraStruXure PDU-Operation and Configuration UPS Page Page Page Page APC Worldwide Customer Support