Startup Procedure

After the electrical wiring connections are verified, power and battery modules can be installed and the SymmetraTM can begin to deliver conditioned power to the output power panel(s).

Securing The Frame - Setting The Leveling Feet

1.Locate the frame in its final operating position.

Note: Leave a minimum of 12” (30 cm) of clearance at the rear of the frame for adequate airflow. Make sure the system enable switch remains accessible.

2.Hand turn all four leveling feet until the pads make contact with the floor.

3.Use a wrench to extend each leveling foot by turning the hex nut two complete turns.

4.Adjust the leveling feet until the frame is level front to back and side to side.

Lower all four leveling feet

Notice!

νAfter the leveling feet are lowered, attempting to move the frame may bend them.

990-7167-001

Start-Up Procedure - Page 1

 

Image 37
Contents 380V/400V/415V 31 Frame Model SYMSTRF3I Life Support Policy Limited WarrantyTable of Contents Page Safety Symbols Safety InformationRadio Frequency Interference Operation SymbolsModels WelcomeFrame Model Description Illustration System Components SymmetraTM Component Description Model Specific Details SYMSTRF3I SYMSTRF3I SymmetraTM Components Description Specific To ModelBasic Operation Glossary of SymmetraTM Terms 8 Introduction Operating Space Requirements Site RequirementsRear Clearance Front ClearanceModels Structural RequirementsEnvironmental Requirements Short-Term Battery Module Storage RequirementsHeat Output VAC Electrical Requirements Input/OutputEPO Specifications Electrical Requirements EPO SwitchElectrical Wiring Overview Receiving and Unpacking SymmetraTM Component Shipping Weight Shipping DimensionsReceiving the SymmetraTM Inspect PackagingMoving The SymmetraTM Frame and Modules Unpacking the SymmetraTM Frame 4 Receiving and Unpacking Model SYMSTRF3I Electrical InstallationElectrical Requirements EPO Switch Wiring RequiredElectrical Wiring Overview Input/Output Wiring Wire Size Input/Output Wiring ProcedureMinimum Emergency Power Off Switch Wiring Required Emergency Power Off Switch Wiring Procedure Bypass Balancing Transformer Wiring Optional Wiring Symbol Description Minimum Wire Gauge Bypass Balance Transformer Wiring Procedure OptionalWiring Verification Procedure Reported Output Voltage OutVHz APC Worldwide Technical Support Telephone Numbers Securing The Frame Setting The Leveling Feet Startup ProcedurePower Module Installation Battery Module Installation System Startup Procedure Configuration Configuration and Advanced OperationDisplay Settings System Settings SetupAdvanced Operation PowerView Interface PowerView Component Description PowerView ComponentsLanguage Chip Replacement Procedure Language ConfigurationTop-Level Menu Screen Startup ScreenStatus ControlSetup PowerView CommandsLogging AccessoriesFunction Options DisplayHelp DiagnosticsWall Mounting the PowerView PowerView Meaning Corrective Action Message Start-Up TroubleshootingPowerView Meaning Corrective Action Message General Alarm PowerView Meaning Corrective Action Message ModuleFailure ThresholdFault PowerView Meaning Corrective Action Message BypassGeneral PowerView Meaning Corrective Action Message6 Troubleshooting Appendix B Module Failure Alarm Indicators Module ReplacementReturning Modules to APC Technical Support & Obtaining Replacement ModuleReplacement Battery Module Verification Battery Module ReplacementReplacement Module Verification Power Module ReplacementReplacement MIM Verification Main Intelligence Module ReplacementRedundant Intelligence Module Replacement Replacement RIM Verification6 Module Replacement Appendix C Input Specifications SpecificationsOperation Physical Specifications Output SpecificationsCompliance Specifications Page Tel0800 180