Allied Telesis 9103, 9102, 9100, 9101 manual Attaching the Extension Brackets and Rear Brackets

Page 17

9102/3 Mounting Options

Shelf Mounting Options

1.5.2.3 Attaching the Extension Brackets and Rear Brackets

Caution: Two persons are required to mount the 9102/3, with one person in front of and another person behind the unit.

Note that the rear brackets, as shown in Figure 1-8, are rotationally symmetrical; when facing the rear of the unit, the flange is on the bottom on the right, and top on the left. (This allows adequate clearance for removal of the power converter if needed.)

1.The person in front of the unit moves the 9102/3 into position.

2.While the person behind the unit holds the unit steady, the person in front of the unit attaches the unit to the front rack using four mounting screws. (Install the top screws and then the bottom screws.)

3.The person behind the unit attaches the Rear Brackets as shown in Figure 1-8. Adjust the brackets so they are flush with the rear rack. Attach the four nuts loosely since they will move slightly when the rear mounting screws are turned.

4.The person behind the unit attaches the unit to the rear rack using four mounting screws. (Install the top screws and then the bottom screws.). The rear bracket should slide slightly as the screws are tightened.

5.Tighten the four nuts of the Rear Bracket.

FIGURE 1-8Rear Bracket Attachment for 9102/3

Telesyn 9100 Installation Guide (Installation of Allied Telesyn 9100)

1-13

Image 17
Contents Page About this Guide Reason for UpdateWho Should Read This Guide? Table of Contents Appendix Allied Telesyn 9100 Configuration Installation Overview forSelecting a Site for Following Procedures for the 9101, 9102,2Site Requirements for Allied Telesyn 1 9101 Site Requirements3Site Requirements for Allied Telesyn 9102 2 9102/9103 Site Requirements9102/9103 Site Requirements Selecting a Site for 4Part Checklist for Setup Checklist5Customer Item Checklist 1 9101 Parts Included in Order2 9102 / 9103 Parts Included in Order 6Part Checklist for7Part Checklist for 1 9101 Mounting Options 8Customer Item ChecklistShelf Mounting Options 4Front mount option for Shelf Mounting Options Center Mounting Option 6Front Mount for 9102/3 2 9102/3 Mounting Options7Mid-Mount for 9102/3 Attaching the Extension Brackets and Rear Brackets Overview Wall Mounting OptionSafety Guidelines Allied Telesyn 9100 Installation SafetyInstalling the Wall Mount Electrostatic Discharge Safety Precautions While Working with ElectricityPrecautions and Conformance Standards Power and Grounding Cautions Installing Power and Ground forLaser Safety Instructions Connect Power and Ground Installing Power and Ground for Connect Power and Ground 129100 PEM plug with connections indicated Connect the -48VDC office power supply to the 9101 PEM plugApply and Check Power DC Power Supply Connect to Power Source Single or DualApply and Check Power AC Power Supply Alarm Connections 9101 OptionalInstall the CFC12 Install Card ModulesInstall the SFP Module Install the Service ModuleInstall Filler Plates FPF Configure Local Terminal or PCOption Default 9Default Asynchronous Port SettingsConnect System Cables Service Modules with RJ21connectors13.4 GE4/FE2 SMs with RJ45 connectorsSMs with Optical connectors Data Management Cable Mgmt Port on CFC12 Apply Power and Check Startup Sequence Page Check management interfaces Check the configurationCheck software load Allied Telesyn Contact Information Adding AC Power ModuleGlossary of Terms Appendix1Registration Information for the Telesyn Telesyn 9100 Inventory Form