Connect the -48VDC office power supply to the 9101 PEM plug. Installing Power and Ground for the 9101

1.8.3 Connect the -48VDC office power supply to the 9101 PEM plug.

1.Loosen the screws.

2.Using cables colored as in Figure 1-12, strip each 1/4 in. (6.5 mm).

3.Insert each cable into its appropriate lug on the PEM plug. Use the figure below to determine the correct lugs.

FIGURE 1-129100 PEM plug with connections indicated

4.Tighten each screw.

5.Carefully dress and tie-wrap or tape the power and ground cables.

6.Ensure that fuses A and B have been removed from the 9100 PEM.

7.Plug the 9100 PEM plug into its connector on the faceplate of the unit. The PEM plug will only fit one way. Tabs on the front of the PEM plug prevent it from being inserted incorrectly.

Telesyn 9100 Installation Guide (Installation of Allied Telesyn 9100)

1-21

Image 25
Contents Page Who Should Read This Guide? Reason for UpdateAbout this Guide Table of Contents Appendix Allied Telesyn 9100 Configuration Installation Overview forSelecting a Site for Following Procedures for the 9101, 9102,2Site Requirements for Allied Telesyn 1 9101 Site Requirements3Site Requirements for Allied Telesyn 9102 2 9102/9103 Site Requirements9102/9103 Site Requirements Selecting a Site for 4Part Checklist for Setup Checklist5Customer Item Checklist 1 9101 Parts Included in Order7Part Checklist for 6Part Checklist for2 9102 / 9103 Parts Included in Order Shelf Mounting Options 8Customer Item Checklist1 9101 Mounting Options 4Front mount option for Shelf Mounting Options Center Mounting Option 6Front Mount for 9102/3 2 9102/3 Mounting Options7Mid-Mount for 9102/3 Attaching the Extension Brackets and Rear Brackets Overview Wall Mounting OptionInstalling the Wall Mount Allied Telesyn 9100 Installation SafetySafety Guidelines Electrostatic Discharge Safety Precautions While Working with ElectricityPrecautions and Conformance Standards Laser Safety Instructions Installing Power and Ground forPower and Grounding Cautions Connect Power and Ground Installing Power and Ground for Connect Power and Ground 129100 PEM plug with connections indicated Connect the -48VDC office power supply to the 9101 PEM plugApply and Check Power DC Power Supply Connect to Power Source Single or DualApply and Check Power AC Power Supply Alarm Connections 9101 OptionalInstall the CFC12 Install Card ModulesInstall the SFP Module Install the Service ModuleInstall Filler Plates FPF Configure Local Terminal or PCOption Default 9Default Asynchronous Port SettingsConnect System Cables Service Modules with RJ21connectorsSMs with Optical connectors SMs with RJ45 connectors13.4 GE4/FE2 Data Management Cable Mgmt Port on CFC12 Apply Power and Check Startup Sequence Page Check software load Check the configurationCheck management interfaces Allied Telesyn Contact Information Adding AC Power ModuleGlossary of Terms Appendix1Registration Information for the Telesyn Telesyn 9100 Inventory Form