Toshiba RAV-SM800XT-E, RAV-SM560XT-E Thicknesses of annealed copper pipes Thickness mm

Page 16

Table 6-2-1 Thicknesses of annealed copper pipes

 

 

 

Thickness (mm)

 

 

 

 

 

Nominal diameter

Outer diameter (mm)

R410A

 

R22

 

 

 

 

 

1/4

6.35

0.80

 

0.80

 

 

 

 

 

3/8

9.52

0.80

 

0.80

 

 

 

 

 

1/2

12.70

0.80

 

0.80

 

 

 

 

 

5/8

15.88

1.00

 

1.00

 

 

 

 

 

(2)Joints

For copper pipes, flare joints or socket joints are used. Prior to use, be sure to remove all contaminants.

a)Flare joints

Flare joints used to connect the copper pipes cannot be used for pipings whose outer diameter exceeds 20 mm. In such a case, socket joints can be used.

Sizes of flare pipe ends, flare joint ends and flare nuts are as shown in Tables 6-2-3 to 6-2-6 below.

b)Socket joints

Socket joints are such that they are brazed for connections, and used mainly for thick pipings whose diameter is larger than 20 mm.

Thicknesses of socket joints are as shown in Table 6-2-2.

Table 6-2-2 Minimum thicknesses of socket joints

Nominal diameter

Reference outer diameter of

Minimum joint thickness

copper pipe jointed (mm)

(mm)

 

 

 

 

1/4

6.35

0.50

 

 

 

3/8

9.52

0.60

 

 

 

1/2

12.70

0.70

 

 

 

5/8

15.88

0.80

 

 

 

6-2-1. Processing of piping materials

When performing the refrigerant piping installation, care should be taken to ensure that water or dust does not enter the pipe interior, that no other oil other than lubricating oils used in the installed air conditioner is used, and that refrigerant does not leak. When using lubricating oils in the piping processing, use such lubricating oils whose water content has been removed. When stored, be sure to seal the container with an airtight cap or any other cover.

(1)Flare Processing procedures and precautions

a)Cutting the pipe

By means of a pipe cutter, slowly cut the pipe so that it is not deformed.

b)Removing burrs and chips

If the flared section has chips or burrs, refrigerant leakage may occur. Carefully remove all burrs and clean the cut surface before installation.

c)Insertion of flare nut

d)Flare processing

Make certain that a clamp bar and copper pipe have been cleaned.

By means of the clamp bar, perform the flare processing correctly.

Use either a flare tool for R410A or conven- tional flare tool.

Flare processing dimensions differ according to the type of flare tool. When using a conven- tional flare tool, be sure to secure “dimension A” by using a gauge for size adjustment.

D

A

Fig. 6-2-1 Flare processing dimensions

– 14 –

Image 16
Contents AIR-CONDITIONER Contents Specifications Indoor UnitOperation characteristic curve Cooling Heating CurrentOutdoor Unit RAV-SM560AT-E RAV-SM800AT-EConstruction Views Outdoor Unit RAV-SM560AT-E Outdoor Unit RAV-SM800AT-E Systematic Refrigerating Cycle Diagram RAV-SM560XT-E / RAV-SM560AT-ERAV-SM800XT-E / RAV-SM800AT-E Indoor unitWiring Diagram Color IdentificationL N Board Specification of Electrical Parts Parts name Type SpecificationsSafety During Installation/Servicing Refrigerant Piping InstallationRefrigerant R410A Piping materials and joints usedOuter diameter mm R410A R22 1 Thicknesses of annealed copper pipes Thickness mmProcessing of piping materials Clutch type Wing nut type Width·m kgf·cm ·m kgf·mRequired tools ToolsGeneral tools Conventional tools can be used 1 Configuration of refrigerant charging Recharging of RefrigerantBrazing of Pipes Characteristics required for flux Types of flux Noncorrosive fluxActivated flux Filler FluxControl Block Diagram OperationWhen power supply is reset Operation mode selectionAir volume control Operation DescriptionCool air discharge preventive control 1 Cold draft preventing controlFreeze preventive control Low temperature release High-temp release controlLouver control Filter sign displayHow to set auto restart function Auto Restart FunctionOperation MotionsHow to cancel auto restart function Power failure during timer operationHow to turn off filter check lamp Filter Check LampInstallation Procedure Installation Diagram of Indoor and Outdoor UnitsUnder Ceiling Installation Console InstallationPrecautions for Safety To Disconnect the Appliance from Main Power SupplyPage Accessory parts Accessory parts and Parts to be procured locallyParts to be procured locally Selection of Installation Place Avoid installing in the following placesInstallation Place Remote controllerRemote controller usage Before Installation Remove the Air inlet grilleInstall the indoor unit Install the Suspension boltsCondition for Installation Piping and Drain Hose InstallationConnect the Flexible pipe 5 to the large pipe Gas side Unit must not decline more than 15 mm in either Cutting a hole and mounting the Installation plateAxis Drain Piping Work DrainageRefrigerant Piping Tightening connection Evacuating Heat insulation For RAV-SM560AT-E model Electrical Work Final Installation Checks LED indication and code checking Environment Troubleshooting Summary of TroubleshootingBefore troubleshooting Troubleshooting procedureSelf-Diagnosis by Remote Control Check Code How to use remote control in service modeJudgement and action No display in the setting at shipment Operation Troubleshooting for Each Check Code 1A error YESError 1C error* Except RAV-SM560AT-E 1E error 1D error1F error Connector normal? TA sensor TC, TCJ sensor Caracteristics-1 Caracteristics-2 Caracteristics-320 TE, TO, TS sensor TD sensor Caracteristics-4Compressor does not operate Inspection procedurePrimary check Cooling and heating model Are all of compressor cords normal? Detachments How to install the Air inlet grilleRemove the Panel arms from the Front panel Open 3 Cap screws and remove the screws How to remove the Drain pan Assembly Pan assembly Refrigeration How to remove the Refrigeration assemblyHow to remove the Multiblade fan Part name Procedures RemarksFan motor No. Part name Procedure Remarks DetachmentProcedure Remarks Requirement Connection with the power terminal Part name Procedure Remarks ‡ Compressor Perform works of items 1 ‚, ƒ, „, … Fan guard Remove the upper cabinet Discharge port cabinet for the heat ex Requirement Part name… Control P.C Remove the inverter box from P.C. board base Loosen the flange nut by turning clock † Compressor Perform works of items , ‚, ƒ, „, Ø4 x 10L , 2 pcs. per one reactor Product Exploded Views and Parts List Indoor Unit E-Parts AssyAir Inlet Grille Inverter 21,22 16,17 Outdoor Unit Inverter Assy, RAV-SM560AT-E 702 TE Sensor TS Sensor To Sensor TD Sensor 701 705 703 704Inverter BOX Outdoor Unit Inverter Assy, RAV-SM800AT-E