Gas Piping

CAUTION

If a flexible gas connector is required or allowed by the authority that has jurisdiction, black iron pipe shall be installed at the gas valve and extend outside the furnace cabinet. The flexible connector can then be added between the black iron pipe and the gas supply line.

WARNING

Do not exceed 600 in−lbs (50 ft−lbs) torque when at- taching the gas piping to the gas valve.

IMPORTANT

Compounds used on threaded joints of gas piping must be resistant to the actions of liquified petro- leum gases.

Leak Check

After gas piping is completed, carefully check all piping connections (factory− and field−installed) for gas leaks. Use a leak detecting solution or other preferred means.

The furnace must be isolated from the gas supply system by closing its individual manual shut-off valve during any pressure testing of the gas supply system at pressures less than or equal to 1/2 psig (3.48 kPa, 14 inches w.c.).

1 − Gas piping may be routed into the unit through either the left- or right-hand side. Supply piping enters into the gas valve from the side of the valve as shown in figure 47.

2 − When connecting gas supply, factors such as length of run, number of fittings and furnace rating must be con- sidered to avoid excessive pressure drop. Table 10 lists recommended pipe sizes for typical applications.

MANUAL MAIN SHUT−OFF VALVE WILL NOT HOLD NORMAL TEST PRESSURE

1/8" N.P.T. PLUGGED TAP

CAP

FURNACE

ISOLATE GAS VALVE

NOTE − Use two wrenches when connecting gas pip- ing to avoid transferring torque to the manifold.

3 − Gas piping must not run in or through air ducts, clothes chutes, chimneys or gas vents, dumb waiters or eleva- tor shafts. Center gas line through piping hole. Gas line should not touch side of unit. See figures 47.

4 − Piping should be sloped 1/4 inch per 15 feet (6mm per 5.6m) upward toward the gas meter from the furnace. The piping must be supported at proper intervals, ev- ery 8 to 10 feet (2.44 to 3.05m), using suitable hangers or straps. Install a drip leg in vertical pipe runs to serve as a trap for sediment or condensate.

5 − A 1/8" N.P.T. plugged tap or pressure post is located on the gas valve to facilitate test gauge connection. See figure 54.

6 − In some localities, codes may require installation of a manual main shut-off valve and union (furnished by in- staller) external to the unit. Union must be of the ground joint type.

FIGURE 46

IMPORTANT

When testing pressure of gas lines, gas valve must be disconnected and isolated. See figure 46. Gas valves can be damaged if subjected to pressures greater than 1/2 psig (3.48 kPa).

WARNING

FIRE OR EXPLOSION HAZARD

Failure to follow the safety warnings exactly could result in serious injury, death, or property damage. Never use an open flame to test for gas leaks. Check all connections using a commercially available soap solution made specifically for leak detection. Some soaps used for leak detection are corrosive to certain metals. Carefully rinse piping thoroughly after leak test has been completed.

Page 30

Image 30
Contents Installation Instructions ML193DF Table of ContentsML193DF Unit Dimensions − inches mm ML193DFControl BOX BAG AssemblyML193DF Parts Arrangement Blower MotorML193DF Gas Furnace Safety InformationDirect Vent Installation NON−DIRECT Vent Shipping and Packing ListUse of Furnace as Construction Heater General Combustion, Dilution & Ventilation AirEquipment in Confined Space − ALL AIR from Inside Shipping Bolt Removal Equipment in Confined Space − ALL AIR from OutsideInstallation − Setting Equipment Setting EquipmentFront Horizontal Back NON−COMBUSTIBLE Floor Opening Size NC‡Combustible Flooring Base Opening Size Side View− Seal the cabinet and check for air leaks Filters Pipe & Fittings SpecificationsPiping and Fittings Specifications Duct SystemOutdoor Termination Kits Usage Piping Suspension Guidelines Joint Cementing ProcedureVenting Practices ScheduleVent Piping Guidelines Minimum Vent Pipe LengthsML193DF MIN. Vent Length Model Maximum Allowable Intake or Exhaust Vent Length in Feet Typical Exhaust Pipe Connections Typical Intake Pipe ConnectionsIntake Exhaust Typical AIR Intake Pipe Connections Inside Corner Detail Inches 305mm or 12 in mmUS Installations1 Canadian Installations2 − On field supplied terminations, a minimum distance Direct Vent Roof Termination KITFLUSH−MOUNT Side Wall Termination KIT 51W11 51mm 76mm Vent Pipe Unconditioned Space Reducer MAY beRequired to Adapt SupportFront View Top ViewExhaust 203mm − 305mm NON−DIRECT Vent Roof Termination KITML193DF NON−DIRECT Vent Application Using Existing Chimney ML193DF with Evaporator Coil To drainTrap / Drain Assembly Using 1/2 PVC or 3/4 PVC Gas Piping Furnace Isolate GAS ValveGAS Pipe Capacity − FT3/HR kL/HR Precautions and Procedures ElectricalElectrostatic Discharge ESD Exterior MAKE−UP BOX FACTORY− Installed Left Side MAKE−UPInterior MAKE−UP BOX BOX InsideTypical ML193DF Field Wiring Diagram Thermostat DesignationsTypical ML193DF Wiring Diagram Integrated Control For Your Safety Read Before OperatingUnit Start−Up Automatic Hot Surface Ignition SystemPage Proper Combustion Gas Pressure AdjustmentGAS Meter Clocking Chart High Altitude Information2286 − 3038m 2286m 3048m73W37 73W81 68W68 74W90 74W91 69W73 Other Unit Adjustments Heat FAN-OFF Time in SecondsNo Jumper Blower Data High Low In. w.g Cfm Watts Cfm Watts cfm WattsService Electrical SHOCK, Fire Or Explosion HazardPage Diagnostic Codes Planned ServiceIgnition Control Board Diagnostic Codes LED #1 Red LED #2 GreenTroubleshooting Heating Sequence of Operation Normal Heating Mode Abnormal Heating ModeHeating Sequence of Operation Heating Sequence Troubleshooting Cooling Sequence of Operation Normal Cooling Mode Abnormal Cooling ModeCooling Sequence of Operation Troubleshooting Continuous Fan Sequence of Operation Continuous Heat Speed FAN Sequence of OperationRepair Parts List Return AIR Duct System Supply AIR Duct Start−Up & Performance Check ListGAS Supply Intake / Exhaust PipeCondensate Line Thermostat Temperature RiseTotal External Static Drain Line Vent PipeRequirements for Commonwealth of Massachusetts LY BELOW. Keep Clear of ALL OBSTRUC- Tions