Jotul GF 100 DV II, GF 200 DV II manual Venting Requirements, Intake Air Restriction

Page 9

GF 100 DV II Nordic QT GF 200 DV II Lillehammer

Venting Requirements

Both stoves may be installed with a vertical or horizontal termination and must conform to the configuration requirements described in this section. Vent components from the manufacturers listed below are approved for use:

Simpson Dura-Vent GS

Selkirk Metalbestos

Security Vent Ltd.

Amerivent Corporation

Use parts of one manufacturer only - DO NOT MIX VENT COMPONENTS FROM DIFFERENT MANUFACTURERS IN THE SAME SYSTEM.

Installation of any components not manufactured or approved by Jøtul or failure to meet all clearance require- ments will void all warranties and could result in prop- erty damage, bodily injury, or serious fire.

The approved vent configurations described in this manual are derived from extensive testing under con- trolled laboratory conditions. Gas appliance performance can be negatively affected by variables present in the installation environment, i.e: atmospheric pressure, strong prevailing winds, adjacent structures and trees, snow accumulation, etc. These conditions should be taken into consideration by the installer and stove owner when planning the vent system design.

IMPORTANT

JOINT SEALING REQUIREMENT: APPLY A 1/8” BEAD OF HIGH-TEMPERATURE SEALANT (SUCH AS MIL-PAC®) TO THE MALE SECTION OF THE INNER

VENT PIPE. THE CEMENT SHOULD FORM A SEAL BETWEEN THE INNER AND OUTER PIPES.

• NEVER MODIFY ANY VENTING COMPONENT, OR USE ANY DAMAGED VENTING PRODUCT.

• THE GAS APPLIANCE AND VENT SYSTEM MUST BE VENTED DIRECTLY TO THE OUTSIDE OF THE BUILDING AND NEVER ATTACHED TO

A CHIMNEY SERVING A SOLID FUEL OR GAS BURNING APPLIANCE. EACH DIRECT VENT GAS APPLIANCE MUST HAVE ITS OWN SEPARATE VENT SYSTEM. COMMON VENT SYSTEMS ARE PROHIBITED.

IF VENTING SYSTEM IS DISASSEMBLED FOR ANY REASON, REINSTALL PER THE INSTRUCTIONS PROVIDED FOR THE INITIAL INSTALLATION.

Intake Air Restriction

You may need to restrict air intake to the burner, depend- ing on the stove vent configuration. Two Side Restrictor Plates and one Rear Restrictor Plate are included in the Miscellaneous Kit for this purpose. Use the following guidelines to determine the proper restriction, if any, for your installation.

Horizontal Termination

No air restriction should be necessary. Do not install the restrictor plates.

Vertical Termination

1.For Any Vertically Terminated Stove - Fig. 5. Remove the Recirculator Plate from the back of the Burner Skirt. It is secured by a single sheet metal screw.

2.Optional Restriction - Fig. 6.

A)Termination less than 8 ft. high:

Install Rear Restrictor Plate. Engage the plate with the two pins on the back of the Burner Skirt.

B)Termination 8 - 15 ft. high:

Install the Side Restrictor Plates, in addition to the Rear Restrictor Plate. The plates are interchangeable. Engage each plate with the pin on either side of the Burner Skirt.

Recirculator Plate

Figure 5. Remove Recirculator Plate.

Rear Restrictor Plate

Side Restrictor Plates

Figure 6. Installing the Air Intake Restrictor Plates.

9

Image 9
Contents Installation and Operation Instructions Welcome to Jøtul Table of Contents GF 100 DV II Miscellaneous Kit Contents Jøtul GF 100 DV II Nordic QT SpecificationsGF 100 DV II Accessories Input RatesGF 200 DV II Miscellaneous Kit Contents Jøtul GF 200 DV II Lillehammer SpecificationsSuggested Tools for Installation and Service Stove SetupRemove the Top Plate Remove the Glass PanelLocation Safety InformationHearth Requirements Glass FrontAlcove Installation Intake Air Restriction Venting RequirementsHorizontal Termination Vertical TerminationHorizontal RUN Vertical Vent TerminationCo-linear Vent Installation These installation requirements must be followedVenting Through a Fireplace Min. / Max. Horizontal Run Horizontal Vent TerminationHorizontal Termination with Vertical Rise Wall Shield InstallationMin inches, U.S. / *12 inches 30 cm can Horizontal Termination ClearanceMobile Home Installation Conversion Kit ContentsTools required Never USE AN Open Flame to Check for GAS Leaks Gas Conversion ProcedureLeak test Gas Supply ConnectionHigh Altitude Adjustment Gas PressureInches water column High Altitude Orifice Chart GF 200 DV II Only Flame Appearance Air Shutter AdjustmentDerating Procedure To adjust the air shutterOptional Wall Thermostat or Remote Control Log Set InstallationRemote Control Proper pilot flame appearance System CheckGlass and Gasket Replacement MaintenanceOnly Use Replacement Kit OperationDate of Purchase Name of InstallerOptional Blower # InstallationBlower Operation Connect power cord to the nearest outletAttach the Blower to the stove Snapstat terminal. See figs.3547a 47b Parts List GF 100 DV II / GF 200 DV II Firebox Assembly 47a47b GF 100 DV II Nordic QT GF 200 DV II Lillehammer GF 100 DV II Nordic QT Cast Iron Parts ListInstall the Lower Panel Optional Antique Brick Panel Kit InstallationInstall the Logset. Refer to pg Replace the Glass FrameControl Valve Lighting InstructionsJøtul North America Jøtul AS