INSTALLATION

UNIT INSTALLATION WITH HORIZONTAL TERMINATION

(Rigid Vent Systems)

Note:

Atopclearanceof3"(76mm)andside&bottom clearance of 2"(51mm) must be maintained; except when passing through a wall, ceil- ing, or at the termination where the use of a firestop or wall thimble reduces the required clearance to 1-1/2" (38mm). We recommend framing a 11"(279mm) x 11"(279mm) (inside dimensions) hole to give structural rigidity for mounting the termination.

Install the vent system according to the manufacturer's instructions included with the components.

Horizontal runs of vent must be supported every 3 feet (0.9meter). Wall straps are available for this purpose.

6)Mark the wall for a 11" x 11" (279mm x 279mm) square hole. The center of the square hole should line up with the center- line of the horizontal pipe. Cut and frame the 11 inch (279mm) square hole in the exterior wall where the vent will be terminated. See diagram 2 for center line requirements.

If the wall being penetrated is constructed of non-combustible material, i.e. masonry block or concrete, an 8" (203mm) diameter hole is acceptable.

7)Ensure that the pipe clearances to combustible materials are maintained (Diagram 5). Install the termination cap.

Note: If installing termination on a vinyl siding covered wall, a vinyl siding standofforfurring stripsmustbeused to ensure that the termination is not recessed into the siding.

INSTALLATION

1)Set the unit in its desired location. Check to determine if wall studs or roof rafters are in the way when the venting system is attached. If this is the case, you may want to adjust the location of the unit. Rough in the gas preferably on the right side of the unit and the electrical (junction block is on the left side) on the left.

2)Direct Vent pipe and fittings are designed with special twist-lock connections to connect the venting system to the appliance fl ue outlet. A twist-lock appliance adaptor is required.

3)In conjunction with the Simpson Dura-Vent Direct Vent GS system. Install the adaptor after the unit is set in its desired location. Put a bead of high temperature silicone inside the outer section of the adapter and a bead of Mill Pack on the inner collar. Slip the adapter over the existing inner and outer fl ue collar. Fasten to the outer collar only with the 3 supplied screws (drilling pilot holes will make this easier).

4)Level the fireplace and fasten it to the framing using nails or screws through the top and side nailing strips.

5)Assemble the desired combination of pipe and elbows to the appliance adaptor and twist-lock for a solid connection.

Note: For best results and optimum performance with each approved venting system, it is highly recommended to apply “Mill-Pac” sealant (supplied) to every inner pipe connection.Failuretodosomayresult in drafting or performance issues not covered under warranty. Silicone (red RTV) is optional.

Diagram 2

Note:

a)The horizontal run of vent must be level, or have a 1/4 inch rise for every 1 foot of run towards the termination. Never allow the vent to run downward. This could cause high temperatures and may present the possibility of a fi re.

b)The location of the horizontal vent termination on an exterior wall must meet all local and national building codes, and must not be blocked or obstructed. See "Exterior Vent Termination Locations" section for more details.

Diagram 5

The four wood screws provided should be re- placed with appropriate fasteners for stucco, brick, concrete, or other types of sidings.

8)Before connecting the horizontal run of vent pipe to the vent termination, slide the Wall Thimble over the vent pipe. The wall thimble is required for all horizontal terminations.

9)Slide the appliance and vent assembly towards the wall carefully inserting the vent pipe into the vent cap assembly. It is important that the vent pipe extends into the vent cap sufficientdistancesoastoresultinaminimum pipe overlap of 1-1/4 inches (32mm). Secure the connection between the vent pipe and the vent cap.

10)Install wall thimble in the center of the 11" (279mm)squareandattachwithwoodscrews (Diagram 7).

Diagram 7

NOTE: A Vent Guard is required when the AstroCap is installed above grade at 7 feet or lower.

Diagram 1

Regency® L676 Direct Vent Gas Fireplace

23

Image 23
Contents Libertytm L676 Gas Fireplace Manufactured Mobile Home Requirements Table of Contents Copy of Safety Decal Safety LabelMA Code CO Detector RequirementsUnit Dimensions Important Message Save These Instructions InstallationGeneral Safety Information Installation ChecklistLocating Your GAS Fireplace Heat Release KITHearth Requirements Manufactured Mobile Home Additional RequirementsClearances Mantel LEG Clearances Mantel ClearancesImportant Header must be metal stud Framing & FinishingPrior to Installation Unit AssemblyFactory set for LP units Venting IntroductionVent Restrictor Position Factory set for NG unitsExterior Vent Termination Requirements FPI Kit # Length Contains Venting ArrangementsRigid Pipe Venting Systems Installation58DVA-16AB 8 Rigid Pipe Cross Reference ChartL676 & L900 Direct Vent Fireplace Allowable Horizontal Terminations Horizontal Venting with Two 2 90o Elbows Vertical Venting with Two 2 90o Elbows Feet Height Vent must be supported at offsetsUnit Installation with Horizontal Termination Minimum Vent Unit Installation With Vertical TerminationThis allows for small adjustments DiagramHorizontal Termination with Flex Vent System Unit InstallationGAS Line Heat Shield Latch Location BACK-UP Battery InstallationHinge Door Heat Shield Power Module Power ModuleConversion KIT #521-969 from NG to LP Clip Heat Shield Using a flat head screw driverPilot ShieldHeat J9 Jumper J9 Jumper LocationRear Log Stand Grate Heat Shield Front BurnerBracket Heat Shield Front Burner Removed Hinge DoorBracket Heat Shield Modulating Coil WiresBottom Brick Panel Heat ShieldCable Tie Pilot ShieldClip Handle with care. do not Force Into Position Brick Panel InstallationBracket Brick Panel Clip Tab Base Brick Panel Slot Outerbox of FireboxBackside of Grate LOG SET InstallationRear Burner Tube Front Burner Tube Complete Log Set Installation Wiring Diagram Aeration AdjustmentOperating Instructions Lighting ProcedureOperating Instructions Matching Remote Handset & Control BOX ID CodeNormal Operating Sounds GAS Appliances Shutdown ProcedureOperation During Power Outage Heat Shield GAS Control ValveCopy of Lighting Plate Instructions Right Side Exterior Brick PanelMaintenance Bracket Hinge Heat Door BACK-UP Battery ReplacementBracket Heat Shield Power Module ReplacementControl Module Control Module ReplacementBracket Hinge Heat Heat Shield Replace the DC sparker DC Sparker ReplacementBattery Cover Unplug the power source Valve Tray ReplacementModulating coil Carefully remove the bottom brick panelValve Description Parts ListMain Assembly Parts List Burner & LOG Assembly Parts List Parts List Parts List Warranty Limited Lifetime WarrantyInstaller Please complete the following information