Regency L676 installation manual Requirements, MA Code CO Detector

Page 5

REQUIREMENTS

MA Code - CO Detector

(for the State of Massachusetts only)

5.08: Modifications to NFPA-54, Chapter 10

(2) Revise 10.8.3 by adding the following additional requirements:

(a)For all side wall horizontally vented gas fueled equipment installed in every dwelling, building or structure used in whole or in part for residential purposes, including those owned or operated by the Commonwealth and where the side wall exhaust vent termination is less than seven (7) feet above finished grade in the area of the venting, including but not limited to decks and porches, the following requirements shall be satisfied:

1.INSTALLATION OF CARBON MONOXIDE DETECTORS. At the time of installation of the side wall horizontal vented gas fueled equipment, the installing plumber or gasfitter shall observe that a hard wired carbon monoxide detector with an alarm and battery back-up is installed on the floor level where the gas equipment is to be installed. In addition, the installing plumber or gasfitter shall observe that a battery operated or hard wired carbon monoxide detector with an alarm is installed on each additional level of the dwelling, building or structure served by the side wall horizontal vented gas fueled equipment. It shall be the responsibility of the property owner to secure the services of qualified licensed professionals for the installation of hard wired carbon monoxide detectors

a. In the event that the side wall horizontally vented gas fueled equipment is installed in a crawl space or an attic, the hard wired carbon monoxide detector with alarm and battery back-up may be installed on the next adjacent floor level.

b. In the event that the requirements of this subdivision can not be met at the time of completion of installation, the owner shall have a period of thirty (30) days to comply with the above requirements; provided, however, that during said thirty (30) day period, a battery operated carbon monoxide detector with an alarm shall be installed.

2.APPROVED CARBON MONOXIDE DETECTORS. Each carbon monoxide detector as required in accordance with the above provisions shall comply with NFPA 720 and be ANSI/UL 2034 listed and IAS certified.

3.SIGNAGE. A metal or plastic identification plate shall be permanently mounted to the exterior of the building at a minimum height of eight

(8) feet above grade directly in line with the exhaust vent terminal for the horizontally vented gas fueled heating appliance or equipment. The sign shall read, in print size no less than one-half (1/2) inch in size, "GAS VENT DIRECTLY BELOW. KEEP CLEAR OF ALL

OBSTRUCTIONS".

4.INSPECTION. The state or local gas inspector of the side wall horizontally vented gas fueled equipment shall not approve the installation unless, upon inspection, the inspector observes carbon monoxide detectors and signage installed in accordance with the provisions of 248 CMR 5.08(2)(a)1 through 4.

(b) EXEMPTIONS: The following equipment is exempt from 248 CMR 5.08(2)(a)1 through 4:

1.The equipment listed in Chapter 10 entitled "Equipment Not Required To Be Vented" in the most current edition of NFPA 54 as adopted by the Board; and

2.Product Approved side wall horizontally vented gas fueled equipment installed in a room or structure separate from the dwelling, building or structure used in whole or in part for residential purposes.

(c)MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM PROVIDED. When the manufacturer of Product Approved side wall horizontally vented gas equipment provides a venting system design or venting system components with the equipment, the instructions provided by the manufacturer for installation of the equipment and the venting system shall include:

1.Detailed instructions for the installation of the venting system design or the venting system components; and

2.A complete parts list for the venting system design or venting system.

(d)MANUFACTURER REQUIREMENTS - GAS EQUIPMENT VENTING SYSTEM NOT PROVIDED. When the manufacturer of a Product Approved side wall horizontally vented gas fueled equipment does not provide the parts for venting the flue gases, but identifies "special venting systems", the following requirements shall be satisfied by the manufacturer:

1.The referenced "special venting system" instructions shall be included with the appliance or equipment installation instructions; and

2.The "special venting systems" shall be Product Approved by the Board, and the instructions for that system shall include a parts list and detailed installation instructions.

(e)A copy of all installation instructions for all Product Approved side wall horizontally vented gas fueled equipment, all venting instructions, all parts lists for venting instructions, and/or all venting design instructions shall remain with the appliance or equipment at the completion of the installation.

Regency® L676 Direct Vent Gas Fireplace

5

INSTALLATION

Image 5
Contents Libertytm L676 Gas Fireplace Manufactured Mobile Home Requirements Table of Contents Copy of Safety Decal Safety LabelMA Code CO Detector RequirementsUnit Dimensions General Safety Information InstallationInstallation Checklist Important Message Save These InstructionsHearth Requirements Heat Release KITManufactured Mobile Home Additional Requirements Locating Your GAS FireplaceClearances Mantel LEG Clearances Mantel ClearancesImportant Header must be metal stud Framing & FinishingPrior to Installation Unit AssemblyVent Restrictor Position Venting IntroductionFactory set for NG units Factory set for LP unitsExterior Vent Termination Requirements FPI Kit # Length Contains Venting ArrangementsRigid Pipe Venting Systems Installation58DVA-16AB 8 Rigid Pipe Cross Reference ChartL676 & L900 Direct Vent Fireplace Allowable Horizontal Terminations Horizontal Venting with Two 2 90o Elbows Vertical Venting with Two 2 90o Elbows Feet Height Vent must be supported at offsetsUnit Installation with Horizontal Termination This allows for small adjustments Unit Installation With Vertical TerminationDiagram Minimum VentHorizontal Termination with Flex Vent System Unit InstallationGAS Line Hinge Door Heat Shield Power Module BACK-UP Battery InstallationPower Module Heat Shield Latch LocationConversion KIT #521-969 from NG to LP Clip Heat Shield Using a flat head screw driverPilot ShieldHeat J9 Jumper J9 Jumper LocationBracket Heat Shield Front Burner Removed Heat Shield Front BurnerHinge Door Rear Log Stand GrateBottom Brick Panel Modulating Coil WiresHeat Shield Bracket Heat ShieldCable Tie Pilot ShieldClip Handle with care. do not Force Into Position Brick Panel InstallationBracket Brick Panel Clip Tab Base Brick Panel Slot Outerbox of FireboxBackside of Grate LOG SET InstallationRear Burner Tube Front Burner Tube Complete Log Set Installation Wiring Diagram Aeration AdjustmentOperating Instructions Lighting ProcedureMatching Remote Handset & Control BOX ID Code Operating InstructionsNormal Operating Sounds GAS Appliances Shutdown ProcedureOperation During Power Outage Copy of Lighting Plate Instructions GAS Control ValveRight Side Exterior Brick Panel Heat ShieldMaintenance Bracket Hinge Heat Door BACK-UP Battery ReplacementBracket Heat Shield Power Module ReplacementControl Module Control Module ReplacementBracket Hinge Heat Heat Shield Replace the DC sparker DC Sparker ReplacementBattery Cover Unplug the power source Valve Tray ReplacementModulating coil Carefully remove the bottom brick panelValve Description Parts ListMain Assembly Parts List Burner & LOG Assembly Parts List Parts List Parts List Warranty Limited Lifetime WarrantyInstaller Please complete the following information