Installation Procedures
Installation Procedure Overview
This section provides the basic steps to install the InfraStruXure power and rack components. Follow the references provided with each step for detailed instructions.
Warning: Do not begin installing your InfraStruXure system without an APC Field Service Engineer present.
Note: Search all boxes and packaging to make sure that they are empty before discarding.
1.Determine the correct placement of the system components by studying the InfraStruXure
Warning: If installing InfraStruXure on a raised floor, make sure that the
2.Level the PDU, UPS, NetShelter, and XR Battery Enclosures, using the
See “Level the PDU, UPS, NetShelter, and XR Battery Enclosures” on page 10 for detailed instructions.
3.Exchange side panels and run battery communication cables, if applicable. See “Exchange Side Panels” on page 11 for detailed instructions.
4.Join adjacent enclosures.
For instructions on joining the PDU, UPS, and XR Battery Enclosure see “Join the PDU, UPS, and XR Battery Enclosures” on page 13.
For instructions on joining adjacent NetShelter VX Enclosures, see the installation manual included with your enclosures.
5. Ensure total power off.
See “Total Power Off” on page 3 for detailed instructions.