Specifications
40 kW InfraStruXure PDU
Electrical |
|
|
|
|
|
|
|
Input |
|
|
|
|
|
|
|
Nominal Voltage Requirements | 208/120 V | 480/277 V | 600/346 V |
Nominal Current | 125 A | 54 A | 43 A |
Frequency | |||
Voltage Configuration |
|
|
|
Transformer | 3W + G + GEC |
|
|
Without Transformer | 4W + G |
|
|
Upstream Circuit Breaker †† | 175 AT | 80 AT | 60 AT |
Main Input Conductor Size‡ | 3/0 AWG | #3 AWG | #4 AWG |
UPS Breaker Size | 175 AT | 175 AT | 175 AT |
Maximum Continuous Current | 155 A | 67 A | 54 A |
Grounding | PE node (from AC or floor grid) |
| |
|
|
|
|
Output |
|
|
|
|
|
|
|
Voltage AC |
|
| |
Nominal Voltage | 208:120 V WYE |
|
|
UPS Breaker Size | 150 AT | 150 AT | 150 AT |
Max. Distribution Breaker Size | 150 AT | 150 AT | 150 AT |
Number of Distribution Panels | 2 × 225A, 42- position |
| |
Full Load Rating | 40 kW | 40 kW | 40 kW |
Max. Contin Current + 125% overload | 139 A | 139 A | 139 A |
Nominal Current | 111 A | 111 A | 111 A |
Internal Static Switch Fuses† | 175 A |
|
|
|
|
| |
PDU Current | Determined by UPS |
|
|
Grounding | Separately derived neutral/ground bond |
| |
|
|
|
|
Wiring |
|
|
|
|
|
|
|
UPS to PDU | 3W + G (1/0 AWG) |
|
|
PDU to Distribution Panels | 4W + G (1/0 AWG) |
|
|
Distribution Panels to Racks/Power Strips | 4W + G (12 AWG) |
|
|
Power Cable Connections |
| ||
|
|
|
|
InfraStruXure System - Installation and | 41 |