APC 480, 208, 600 manual See Start-Up Procedure on page 29 for detailed instructions

Page 12

Installation Procedures: Installation Procedure Overview

6. Connect utility conductors to the PDU.

For instructions, see “Connect Utility Conductors to the PDU” on page 14.

7. Connect AC power and control wiring.

See “Connect AC Power and Control Wiring” on page 18 for detailed instructions.

8. Connect DC power wiring, if applicable.

See “Connect DC Power Wiring, if Applicable” on page 20 for detailed instructions.

9 . Connect an EPO switch to the PDU user connection plate

See “Connect an Emergency Power Off Switch” on page 22 for detailed instructions.

10. Connect User Contact Inputs and Relay Outputs to the PDU user connection plate.

See “Connect User Input Contacts and Relay Outputs to the User Connection Plate” on page 24 for detailed instructions.

11. Install Shielding Troughs, Shielding Partitions, and Cable Ladders.

For instructions, see the manuals included with your Shielding Troughs, Shielding Partitions, and Cable Ladders.

12.Install the Rack Automatic Transfer Switches (ATS), Rack Power Distribution Units, and other InfraStruXure rack-mount devices.

For instructions, see the manuals included with your Rack ATS, Rack PDU, or other InfraStruXure rack-mount device.

13. Route and attach power cables to each Rack ATS and/or Rack PDU.

See “Route and Attach Power Cables to the Racks” on page 25 for detailed instructions.

14. Route and attach communication cables to the InfraStruXure Manager hub (or switch).

See “Route Data Cables to the InfraStruXure Manager Hub (or Switch)” on page 28 for detailed instructions.

15.Start the system.

Only qualified, APC-trained personnel may perform a system start-up.

See “Start-Up Procedure” on page 29 for detailed instructions.

8

InfraStruXure System - Installation and Start-Up

Image 12
Contents Installation and Start-Up About this Manual Contents Specifications Safety Symbols used in this manualInstallation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPO EMISite Planning Space ConsiderationsPage Installation Procedures Installation Procedure OverviewSee Start-Up Procedure on page 29 for detailed instructions Tools Required Level the PDU, UPS, NetShelter, and XR Battery Enclosures Exchange Side Panels Exchange Side PanelsConnect Battery Enclosure communication cables Join the PDU, UPS, and XR Battery Enclosures Access the PDU Main Input switch Connect Utility Conductors to the PDUAttach conduit to the PDU for the input conductors Install a circuit breaker Input Voltage Circuit Breaker AmperageRoute the input conductors to the Main Input switch Connect input conductorsGEC Connect AC Power and Control Wiring PDUConnect control wiring Connect DC Power Wiring, if Applicable Cascade XR Battery EnclosuresXR Battery Enclosure Connect an Emergency Power Off Switch OverviewConnect an EPO switch to the user connection plate Overview Route and Attach Power Cables to the Racks Overhead WiringUnder Floor Wiring For single-feed devices within aInfraStruXure System Installation and Start-Up Route Data Cables to the InfraStruXure Manager Hub or Switch Apply power to the system Safety warningsHeavy Use two people to lift and install power modules Start-Up Procedure Apply power to the system Verify UPS battery operation Control MenuTop-Level Menu Verify proper voltage and phase rotation at the UPS Start the UPSFuel % Load % 208V out000V 60Hz Runtime 1hr 2m Verify bypass operation Confirm Yes, UPS into Bypass No, Abort Power the PDU Distribution Breakers Ensure that the Q2 circuit breaker on the PDU is closed onConfigure the InfraStruXure Manager Page Specifications KW InfraStruXure PDUPD40F6FK1-M PD40G6FK1-M PD40L6FK1-M Environmental APC Worldwide Customer Support 990-1483C03/2008