Installation Procedures: Connect DC Power Wiring, if Applicable

Connect power cables from the XR Battery Enclosure to the Symmetra PX UPS

1.Route the XR Battery Enclosure DC output cables to the Symmetra PX UPS through the hole in the adjacent side panels.

2.Connect the XR Battery Enclosure DC output cables to the Symmetra PX UPS DC input terminal [(+) to (+), (CT) to (CT), (–) to (–)].

Tighten the lugs on the terminals only to the torque specified: the power terminal lug diameter is 8 mm with a torque value of 53 lb/in (6Nm).

3.Connect the XR Battery Enclosure ground cable to the Symmetra PX UPS ground stud through the hole in the adjacent side panels.

XR (GND)

 

XR (CT)

pxb0006a

XR (–)

 

XR (+)

 

XR Battery Enclosure

Symmetra PX UPS

InfraStruXure System - Installation and Start-Up

21

Image 25
Contents Installation and Start-Up About this Manual Contents Specifications Symbols used in this manual SafetyMaintenance performed while the PDU is receiving input power Installation/MaintenanceTotal Power Off EMI Emergency Power Off EPOSpace Considerations Site PlanningPage Installation Procedure Overview Installation ProceduresSee Start-Up Procedure on page 29 for detailed instructions Tools Required Level the PDU, UPS, NetShelter, and XR Battery Enclosures Exchange Side Panels Exchange Side PanelsConnect Battery Enclosure communication cables Join the PDU, UPS, and XR Battery Enclosures Connect Utility Conductors to the PDU Access the PDU Main Input switchAttach conduit to the PDU for the input conductors Input Voltage Circuit Breaker Amperage Install a circuit breakerConnect input conductors Route the input conductors to the Main Input switchGEC PDU Connect AC Power and Control WiringConnect control wiring Cascade XR Battery Enclosures Connect DC Power Wiring, if ApplicableXR Battery Enclosure Overview Connect an Emergency Power Off SwitchConnect an EPO switch to the user connection plate Overview Overhead Wiring Route and Attach Power Cables to the RacksFor single-feed devices within a Under Floor WiringInfraStruXure System Installation and Start-Up Route Data Cables to the InfraStruXure Manager Hub or Switch Safety warnings Apply power to the systemHeavy Use two people to lift and install power modules Start-Up Procedure Apply power to the system Control Menu Verify UPS battery operationTop-Level Menu Start the UPS Verify proper voltage and phase rotation at the UPSFuel % Load % 208V out000V 60Hz Runtime 1hr 2m Verify bypass operation Confirm Yes, UPS into Bypass No, Abort Ensure that the Q2 circuit breaker on the PDU is closed on Power the PDU Distribution BreakersConfigure the InfraStruXure Manager Page KW InfraStruXure PDU SpecificationsPD40F6FK1-M PD40G6FK1-M PD40L6FK1-M Environmental 990-1483C APC Worldwide Customer Support03/2008