Connect an Emergency Power Off Switch

Overview

To provide a mechanism for

emergency power off, attach a

remote switch (not included) to the EPO interface on the PDU

monitoring unit. The EPO interface () is connected to the

PDU Main Input switch () and to the UPS internal EPO switch

().

When the EPO is activated, the

main input breaker to the PDU transformer is opened, the UPS

DC Disconnect breaker is opened,

and the UPS System Enable switch is turned off. In this sequence, there is no power from the PDU transformer and there is no power from the UPS inverters and batteries.

Note: Contact closure is recommended.

Connecting the switch. The Emergency Power Off (EPO) switch connects to the PDU user connection plate. The figure on the right shows the location of the user connection plate on the roof of the PDU. Connect a switch using one of three following connections:

Contact closure

24Vac

• 24Vdc

Note: APC offers an optional InfraStruXure EPO System (EPW9). Contact your APC sales representative, or visit the APC Web site (www.apc.com) for more information.

22

InfraStruXure System - Installation and Start-Up

Image 26
Contents Installation and Start-Up About this Manual Contents Specifications Safety Symbols used in this manualInstallation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPO EMISite Planning Space ConsiderationsPage Installation Procedures Installation Procedure OverviewSee Start-Up Procedure on page 29 for detailed instructions Tools Required Level the PDU, UPS, NetShelter, and XR Battery Enclosures Exchange Side Panels Exchange Side PanelsConnect Battery Enclosure communication cables Join the PDU, UPS, and XR Battery Enclosures Attach conduit to the PDU for the input conductors Access the PDU Main Input switchConnect Utility Conductors to the PDU Install a circuit breaker Input Voltage Circuit Breaker AmperageRoute the input conductors to the Main Input switch Connect input conductorsGEC Connect AC Power and Control Wiring PDUConnect control wiring Connect DC Power Wiring, if Applicable Cascade XR Battery EnclosuresXR Battery Enclosure Connect an Emergency Power Off Switch OverviewConnect an EPO switch to the user connection plate Overview Route and Attach Power Cables to the Racks Overhead WiringUnder Floor Wiring For single-feed devices within aInfraStruXure System Installation and Start-Up Route Data Cables to the InfraStruXure Manager Hub or Switch Apply power to the system Safety warningsHeavy Use two people to lift and install power modules Start-Up Procedure Apply power to the system Verify UPS battery operation Control MenuTop-Level Menu Verify proper voltage and phase rotation at the UPS Start the UPSFuel % Load % 208V out000V 60Hz Runtime 1hr 2m Verify bypass operation Confirm Yes, UPS into Bypass No, Abort Power the PDU Distribution Breakers Ensure that the Q2 circuit breaker on the PDU is closed onConfigure the InfraStruXure Manager Page Specifications KW InfraStruXure PDUPD40F6FK1-M PD40G6FK1-M PD40L6FK1-M Environmental 03/2008 APC Worldwide Customer Support990-1483C