Exchange Side Panels
Before installing the InfraStruXure PDU, Symmetra PX UPS, and XR Battery Enclosure, exchange side panels so that the adjacent panels will have matching holes for joining the enclosures together and for routing input and output wiring between them. The following side panels will need to be exchanged:
•Adjacent side panels of a PDU and UPS
•Adjacent side panels of a XR Battery Enclosure and a UPS
•Adjacent side panels of two XR Battery Enclosures
psx0136a
Exchange Side Panels
1. Detach the ground wires from the side panels.
gen0303a
2.Remove the solid side panels from the side of the UPS that will be adjacent to the PDU and the XR Battery Enclosure in the planned configuration.
InfraStruXure System - Installation and | 11 |