APC 480, 208, 600 manual Verify UPS battery operation, Control Menu

Page 36

Start-Up Procedure: Apply power to the system

Verify UPS battery operation

1.Read the messages displayed on the Symmetra PX UPS display interface. Note any alarms and verify that they are appropriate for start-up conditions.

2.Command the UPS to apply power to the load:

a.Press the ESC key to open the top-level menu.

b.Select Control, and press the ENTER key.

c.Select Turn Load On from the Control menu, and press the ENTER key.

d.On the next screen: select Yes, UPS Load ON, and press the ENTER key.

The interface will display the following screen:

The interface will display the following fault message:

e. Select Start Now, and press the ENTER key.

The interface will display the following screen:

The LOAD ON LED illuminates and the interface displays the following screen:

Top-Level Status Screen

Fuel %

Load %

In 208V out000V 60Hz Runtime: 1hr 2m

Top-Level Menu

Control Logging

Status Display

Setup Diags

Accessories Help

Control Menu

UPS Into Bypass

Do Self Test

Simulate Power Fail

Graceful Reboot

Graceful Turn Off

Start Runtime Cal

Turn Load On

Confirmation Screen

Confirm

Yes, UPS Load ON

No, Abort

UPS has been

commanded to turn load power on...

Low/No AC input

Start up on Batt?

Start Now

Abort Start-up

UPS has been

commanded to turn load power on...

UPS load is on

Press any key...

After you have verified that the UPS operates correctly in battery operation, shut down the UPS:

32

InfraStruXure System - Installation and Start-Up

Image 36
Contents Installation and Start-Up About this Manual Contents Specifications Safety Symbols used in this manualInstallation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPO EMISite Planning Space ConsiderationsPage Installation Procedures Installation Procedure OverviewSee Start-Up Procedure on page 29 for detailed instructions Tools Required Level the PDU, UPS, NetShelter, and XR Battery Enclosures Exchange Side Panels Exchange Side PanelsConnect Battery Enclosure communication cables Join the PDU, UPS, and XR Battery Enclosures Access the PDU Main Input switch Connect Utility Conductors to the PDUAttach conduit to the PDU for the input conductors Install a circuit breaker Input Voltage Circuit Breaker AmperageRoute the input conductors to the Main Input switch Connect input conductorsGEC Connect AC Power and Control Wiring PDUConnect control wiring Connect DC Power Wiring, if Applicable Cascade XR Battery EnclosuresXR Battery Enclosure Connect an Emergency Power Off Switch OverviewConnect an EPO switch to the user connection plate Overview Route and Attach Power Cables to the Racks Overhead WiringUnder Floor Wiring For single-feed devices within aInfraStruXure System Installation and Start-Up Route Data Cables to the InfraStruXure Manager Hub or Switch Apply power to the system Safety warningsHeavy Use two people to lift and install power modules Start-Up Procedure Apply power to the system Verify UPS battery operation Control MenuTop-Level Menu Verify proper voltage and phase rotation at the UPS Start the UPSFuel % Load % 208V out000V 60Hz Runtime 1hr 2m Verify bypass operation Confirm Yes, UPS into Bypass No, Abort Power the PDU Distribution Breakers Ensure that the Q2 circuit breaker on the PDU is closed onConfigure the InfraStruXure Manager Page Specifications KW InfraStruXure PDUPD40F6FK1-M PD40G6FK1-M PD40L6FK1-M Environmental APC Worldwide Customer Support 990-1483C03/2008