Installation Procedures: Connect an Emergency Power Off Switch
Connect an EPO switch to the user connection plate
1.Connect the switch to the EPO connection point terminals located on the bottom side of the PDU user connection plate. Read the label next to the terminal block to determine which terminals to connect to for the signal type you are using:
–Contact
External set of
Normally Open Dry Contacts
– Contact
External set of
Normally Closed Dry Contacts
–
External set of
Normally Open Dry Contacts
24V AC or DC Power Supply
2.Verify that the EPO DIP switches on the PDU monitoring unit are configured properly for the signal type you are using. The labels above the switches and the figure below show the correct settings for both the Normally Open (NO) and Normally Closed (NC) position.
Location of switches on PDU monitoring unit
See the Operation Manual for information on how to test the EPO.
InfraStruXure System - Installation and | 23 |