APC 600, 480, 208 manual Route Data Cables to the InfraStruXure Manager Hub or Switch

Page 32

Route Data Cables to the InfraStruXure Manager Hub (or Switch)

1.Connect a CAT-5 network cable (provided) to the network or 10BaseT ports on your APC InfraStruXure devices. The following devices need to be connected:

Automatic Transfer Switch

Environmental Monitoring Unit

Rack PDU

Symmetra PX UPS

InfraStruXure PDU

2.Run the connected CAT-5 network cables through the data cable troughs to the InfraStruXure Manager Hub (or Switch).

3.Connect each device’s network cable to any available station port in the InfraStruXure Manager Hub (or Switch). Station ports are those with an x after the number (e.g. 2x).

28

InfraStruXure System - Installation and Start-Up

Image 32
Contents Installation and Start-Up About this Manual Contents Specifications Safety Symbols used in this manualInstallation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPO EMISite Planning Space ConsiderationsPage Installation Procedures Installation Procedure OverviewSee Start-Up Procedure on page 29 for detailed instructions Tools Required Level the PDU, UPS, NetShelter, and XR Battery Enclosures Exchange Side Panels Exchange Side PanelsConnect Battery Enclosure communication cables Join the PDU, UPS, and XR Battery Enclosures Attach conduit to the PDU for the input conductors Access the PDU Main Input switchConnect Utility Conductors to the PDU Install a circuit breaker Input Voltage Circuit Breaker AmperageRoute the input conductors to the Main Input switch Connect input conductorsGEC Connect AC Power and Control Wiring PDUConnect control wiring Connect DC Power Wiring, if Applicable Cascade XR Battery EnclosuresXR Battery Enclosure Connect an Emergency Power Off Switch OverviewConnect an EPO switch to the user connection plate Overview Route and Attach Power Cables to the Racks Overhead WiringUnder Floor Wiring For single-feed devices within aInfraStruXure System Installation and Start-Up Route Data Cables to the InfraStruXure Manager Hub or Switch Apply power to the system Safety warningsHeavy Use two people to lift and install power modules Start-Up Procedure Apply power to the system Verify UPS battery operation Control MenuTop-Level Menu Verify proper voltage and phase rotation at the UPS Start the UPSFuel % Load % 208V out000V 60Hz Runtime 1hr 2m Verify bypass operation Confirm Yes, UPS into Bypass No, Abort Power the PDU Distribution Breakers Ensure that the Q2 circuit breaker on the PDU is closed onConfigure the InfraStruXure Manager Page Specifications KW InfraStruXure PDUPD40F6FK1-M PD40G6FK1-M PD40L6FK1-M Environmental 03/2008 APC Worldwide Customer Support990-1483C