APC 208, 480, 600 manual Configure the InfraStruXure Manager

Page 43

Start-Up Procedure: Apply power to the system

2. Close (turn ON) the PDU distribution panel breakers.

Note: When the distribution panel circuit breakers are closed, the PDU power cables and connected equipment are energized.

Configure the InfraStruXure Manager

Once all equipment is installed, the network cables are connected to the InfraStruXure Manager hub (or switch), and start-up of the system is complete, configure the InfraStruXure Manager.

For instructions, see the InfraStruXure Manager Installation and Quick-Startmanual included with your InfraStruXure Manager.

Note: If you use PowerChute Network Shutdown (PCNS) software with your InfraStruXure UPS, your UPS must have a connection to the “User LAN” (public network) for PCNS to function correctly. If the Network Management Card installed in your UPS is connected to the InfraStruXure Manager’s “APC LAN,” you must install a second Network Management Card in your UPS and connect it to the “User LAN”

(public network) to use PCNS.

InfraStruXure System - Installation and Start-Up

39

Image 43
Contents Installation and Start-Up About this Manual Contents Specifications Symbols used in this manual SafetyMaintenance performed while the PDU is receiving input power Installation/MaintenanceTotal Power Off EMI Emergency Power Off EPOSpace Considerations Site PlanningPage Installation Procedure Overview Installation ProceduresSee Start-Up Procedure on page 29 for detailed instructions Tools Required Level the PDU, UPS, NetShelter, and XR Battery Enclosures Exchange Side Panels Exchange Side PanelsConnect Battery Enclosure communication cables Join the PDU, UPS, and XR Battery Enclosures Connect Utility Conductors to the PDU Access the PDU Main Input switchAttach conduit to the PDU for the input conductors Input Voltage Circuit Breaker Amperage Install a circuit breakerConnect input conductors Route the input conductors to the Main Input switchGEC PDU Connect AC Power and Control WiringConnect control wiring Cascade XR Battery Enclosures Connect DC Power Wiring, if ApplicableXR Battery Enclosure Overview Connect an Emergency Power Off SwitchConnect an EPO switch to the user connection plate Overview Overhead Wiring Route and Attach Power Cables to the RacksFor single-feed devices within a Under Floor WiringInfraStruXure System Installation and Start-Up Route Data Cables to the InfraStruXure Manager Hub or Switch Safety warnings Apply power to the systemHeavy Use two people to lift and install power modules Start-Up Procedure Apply power to the system Control Menu Verify UPS battery operationTop-Level Menu Start the UPS Verify proper voltage and phase rotation at the UPSFuel % Load % 208V out000V 60Hz Runtime 1hr 2m Verify bypass operation Confirm Yes, UPS into Bypass No, Abort Ensure that the Q2 circuit breaker on the PDU is closed on Power the PDU Distribution BreakersConfigure the InfraStruXure Manager Page KW InfraStruXure PDU SpecificationsPD40F6FK1-M PD40G6FK1-M PD40L6FK1-M Environmental 990-1483C APC Worldwide Customer Support03/2008