Start-Up Procedure

Apply power to the system

Safety warnings

This section provides instructions on how to perform a system start-up. Do not skip any steps in this procedure.

Electrical Hazard: Only APC Field Service Engineers or qualified, APC-trained personnel may perform a system start-up. Ensure that all power is off. See “Total Power Off” on page 3.

Warning: Do not install any batteries into the XR Battery Enclosure or power modules into the Symmetra PX UPS until instructed to do so.

1.Set the upstream main utility input circuit breaker to ON.

2.Ensure A-B-C clockwise phase rotation at the top of the Main Input switch on the PDU, using a phase rotation meter.

3.Set the Main Input switch on the PDU to ON.

4.Verify A-B-C clockwise phase rotation at the top of the primary winding of the transformer, using a phase rotation meter.

5.Verify that the proper voltage is present on the secondary

winding of the transformer

(208 V, metered phase-to-phase), using a true RMS voltmeter.

gen0168a

InfraStruXure System - Installation and Start-Up

29

Image 33
Contents Installation and Start-Up About this Manual Contents Specifications Symbols used in this manual SafetyMaintenance performed while the PDU is receiving input power Installation/MaintenanceTotal Power Off EMI Emergency Power Off EPOSpace Considerations Site PlanningPage Installation Procedure Overview Installation ProceduresSee Start-Up Procedure on page 29 for detailed instructions Tools Required Level the PDU, UPS, NetShelter, and XR Battery Enclosures Exchange Side Panels Exchange Side PanelsConnect Battery Enclosure communication cables Join the PDU, UPS, and XR Battery Enclosures Access the PDU Main Input switch Connect Utility Conductors to the PDUAttach conduit to the PDU for the input conductors Input Voltage Circuit Breaker Amperage Install a circuit breakerConnect input conductors Route the input conductors to the Main Input switchGEC PDU Connect AC Power and Control WiringConnect control wiring Cascade XR Battery Enclosures Connect DC Power Wiring, if ApplicableXR Battery Enclosure Overview Connect an Emergency Power Off SwitchConnect an EPO switch to the user connection plate Overview Overhead Wiring Route and Attach Power Cables to the RacksFor single-feed devices within a Under Floor WiringInfraStruXure System Installation and Start-Up Route Data Cables to the InfraStruXure Manager Hub or Switch Safety warnings Apply power to the systemHeavy Use two people to lift and install power modules Start-Up Procedure Apply power to the system Control Menu Verify UPS battery operationTop-Level Menu Start the UPS Verify proper voltage and phase rotation at the UPSFuel % Load % 208V out000V 60Hz Runtime 1hr 2m Verify bypass operation Confirm Yes, UPS into Bypass No, Abort Ensure that the Q2 circuit breaker on the PDU is closed on Power the PDU Distribution BreakersConfigure the InfraStruXure Manager Page KW InfraStruXure PDU SpecificationsPD40F6FK1-M PD40G6FK1-M PD40L6FK1-M Environmental APC Worldwide Customer Support 990-1483C03/2008