APC 480, 208, 600 manual Power the PDU Distribution Breakers

Page 42

Start-Up Procedure: Apply power to the system

6. Close (turn ON) the Q2 circuit breaker on the InfraStruXure PDU.

Note: The H3 LED above the Q3 circuit breaker illuminates, indicating that it is safe to operate the Q3 circuit breaker.

7. Open (turn OFF) the Q3 circuit breaker on the InfraStruXure PDU.

8. Command the UPS out of static bypass operation through the UPS display interface:

a. Press the ESC key at the top-level status screen to open the top-level menu and have access to eight submenus.

b. Select Control, and press the ENTER key.

c. Select UPS Out of Bypass on the Control menu, and press the ENTER key.

On the next screen: select Yes, UPS out of Bypass, and press the ENTER key.

Power the PDU Distribution Breakers

1. Ensure that the Q2 circuit breaker on the PDU is closed (ON).

Note: When Q2 is closed, the PDU distribution panel is energized.

38

InfraStruXure System - Installation and Start-Up

Image 42
Contents Installation and Start-Up About this Manual Contents Specifications Safety Symbols used in this manualInstallation/Maintenance Maintenance performed while the PDU is receiving input powerTotal Power Off Emergency Power Off EPO EMISite Planning Space ConsiderationsPage Installation Procedures Installation Procedure OverviewSee Start-Up Procedure on page 29 for detailed instructions Tools Required Level the PDU, UPS, NetShelter, and XR Battery Enclosures Exchange Side Panels Exchange Side PanelsConnect Battery Enclosure communication cables Join the PDU, UPS, and XR Battery Enclosures Access the PDU Main Input switch Connect Utility Conductors to the PDUAttach conduit to the PDU for the input conductors Install a circuit breaker Input Voltage Circuit Breaker AmperageRoute the input conductors to the Main Input switch Connect input conductorsGEC Connect AC Power and Control Wiring PDUConnect control wiring Connect DC Power Wiring, if Applicable Cascade XR Battery EnclosuresXR Battery Enclosure Connect an Emergency Power Off Switch OverviewConnect an EPO switch to the user connection plate Overview Route and Attach Power Cables to the Racks Overhead WiringUnder Floor Wiring For single-feed devices within aInfraStruXure System Installation and Start-Up Route Data Cables to the InfraStruXure Manager Hub or Switch Apply power to the system Safety warningsHeavy Use two people to lift and install power modules Start-Up Procedure Apply power to the system Verify UPS battery operation Control MenuTop-Level Menu Verify proper voltage and phase rotation at the UPS Start the UPSFuel % Load % 208V out000V 60Hz Runtime 1hr 2m Verify bypass operation Confirm Yes, UPS into Bypass No, Abort Power the PDU Distribution Breakers Ensure that the Q2 circuit breaker on the PDU is closed onConfigure the InfraStruXure Manager Page Specifications KW InfraStruXure PDUPD40F6FK1-M PD40G6FK1-M PD40L6FK1-M Environmental APC Worldwide Customer Support 990-1483C03/2008