General Information - Site Requirements
990-2440 AIS 5000 400V Installation Manual 5
Moving the equipment to site:
Before moving the equipment to the installation site, the following should be checked:
• C an the transport equipment handle the weight of the system?
• Is th ere enough space to transport the system to its final destination?
• C an the raised floor (double floor) handle the weight of the system?
The equipment is delivered on a pallet and can be transported on a fork-lift or a pallet truck.
The UPS is contained in a cubicle with a stable frame. This frame can carry heavy components such
as transformers, chokes etc. The frame can be placed directly on a levelled concrete floor.
Clearance at installation site. The system can be installed with the back to the wall or back-to-
back - however, a distance of minimum 4 inches (approx. 100 mm) between the wall and the UPS is
necessary. 20 inches (approx. 500 mm) is the preferred distance (see below illustration).
A clearance of 20 inches (approx. 500 mm) above the system is necessary to ensure sufficient space
for air circulation.
Clearance; minimum 100 mm – preferably 500 mm.
UPS
UPS