Programming and Set-Up - Programming the UPS

Battery Capacity Test

Make sure the UPS has been in normal operation for at least 8 hours and that the batteries are fully charged before performing this test.

To test the Battery Capacity press and

browse through the menu, using the cursor

keys

or

 

until the display shows:

 

 

 

 

 

(xxx indicates the backup time from the last Battery Capacity test). If this test has not been performed before – or if the test has been aborted, the display shows:

To proceed with the test, press

or

to

abort.

 

 

The display shows:

Wait until the display shows:

a short audible alarm will sound.

Press until the display shows:

(xxx represents the actual backup time in minutes)

Press or wait 20 seconds until the display shows:

If a mains failure occurs during a battery capacity test, the test will immediately abort. No test results will be obtained and the display will show:

Battery Capacity Test: xxx

???

Battery Operation Time > ...min

Normal Operation Load Power xx%

Battery Capacity Test: xxx

Normal Operation Load Power xx%

???

990-2440