DATA SHEET 1

General check

CK; DT: digital tester AT: analog tester OS:oscilloscope WC:watch

Check item

Content

Check point

CK

Standard

Judge

Connection

All connection

1.Transducer-transceiver unit

WC

Refer to

 

 

should be checked

2.Processor unit-Transceiver unit

 

installation

 

 

refering to the

3.Processor unit-Control unit

 

manual

 

 

interconnection

4.Processor unit-Others equipment

 

 

 

 

diagram.

5.Ship’s mains-Power supply

 

 

 

 

 

unit-Processor unit

 

 

 

 

 

 

 

 

 

Grounding

All grounding

1.Monitor unit

WC

Refer to

 

 

should be checked

2.Processor unit

 

installation

 

 

by installation

3.Transceiver unit

 

manual

 

 

manual.

4.Power supply unit

 

 

 

 

 

5.Junction box(Option)

 

 

 

 

 

 

 

 

 

Power Supply(ship’s main voltage)

Unit

Check point

CK

Standard

Result

Judge

Processor unit

CN-A110

 

DT

AC100/110/115/220/230V± 10%

 

 

Transceiver unit

TB-B101

#1---#2

DT

AC90V to AC115V

 

 

Power supply unit

TB-D102

 

DT

AC100/110/115/220/230V± 10%

 

 

Hull unit

TB-C101

 

DT

AC220V

 

 

Note that: The input voltage may be dropped while the capacitors are being charged before transmission. For accurate data, please check the voltages during TX on and off as well when you check the input voltage of a transceiver unit.

The input voltage monitoring circuit in transceiver unit detects low voltage when AC 100V power source drops to 85V. On the other hand, if the input voltage is 120 to 130V, the over voltage flag is set and an alarm is displayed to monitor.

AP-2

Page 69
Image 69
Furuno FSV-24S installation manual Data Sheet