Now weld the two plates together. Weld from left to right (if right-handed). Point the electrode down in he gap between the two plates, keeping the electrodes slightly tilted in the direction of travel.

20°

end view

90°

side view

Watch the molten metal to be sure it distributes itself evenly on both edges and in between the plates.

Fillet Joints

When welding fillet joints, it is very important to hold the electrode at a 45° angle between the two sides, or the metal will not distribute itself evenly.

To make it easier to get the 45° angle, it is best to put the electrode in the holder at a 45° angle, as shown.

45°

Return to Section TOC

Return to Section TOC

Section TOC

Return to Master TOC

Master TOC

Penetration

Unless a weld penetrates close to 100%, a butt joint will be weaker than the material welded together.

1/2"

Poor (12mm) 1/4" (6mm)

1/4"

(6mm)

In this example, the total weld is only 1/2 the thickness of the material; thus, the weld is only approximately half as strong as the metal.

Good

45°

Multiple Pass Welds

Make multiple pass horizontal fillets as shown in the sketch. Put the first bead in the corner with fairly high current. Hold the electrode angle needed to deposit the filler beads as shown putting the final bead against the vertical plate.

 

4

 

2

1

3

2

 

 

1

 

 

Return to

Return to Section TOC

Return to

Return to Master TOC

 

Welding in the Vertical Position

In this example, the joint has been flame beveled or

Welding in the vertical position can be done either ver-

ground prior to welding so that 100% penetration could

tical-up or vertical-down. Vertical-up is used whenev-

be achieved. The weld, if properly made, is as strong

er a large, strong weld is desired. Vertical-down is used

or stronger than the original metal.

primarily on sheet metal for fast, low penetrating welds.

60°

4

3 2

1

1/8" (3.2mm)

Successive passes must be used to build up butt welds on heavier metal.