Portal Design Task List
176 Portal Server 6 2005Q1 Deployment Planning Guide
Conduct Integration and System Test Ensure establishment of integration test environment
Identify test team and assign test scenario ownership
Train team on integration test procedures, roles, and
responsibilities
Review and revise integration test execution schedule, as required
Execute integration test
Identify and document integration test discrepancies
Resolve integration test discrepancies and document
Identify required modifications (such as configuration
enhancements, interfaces, reports)
Re-execute integration tests
Update as required
Track test progress
Obtain test approval
Summarize and communicate results to stakeholders

4. Deployment Production

Confirm Approach Review with stakeholders and establish implementation locations
and configurations
Develop implementation approach
Repeat appropriate tasks from development hardware and software
installation
Review and Update Deployment Review existing documentation of results of tests
Validate scope, objectives, and critical success factors
Update deployment approach
Review and approve deployment
Implement Deployment Review and reconcile system operations
Review organization and system procedures
Promote to production
Update current operations
Revise system release and deployment materials
Provide transition support
Table E -8 Design Task List (6 of 7)
Major Phases and Tasks Subtasks