Portal Design Task List

Table E-8

Design Task List (6 of 7)

 

 

Major Phases and Tasks

Subtasks

 

 

 

Conduct Integration and System Test

Ensure establishment of integration test environment

 

 

• Identify test team and assign test scenario ownership

 

 

• Train team on integration test procedures, roles, and

 

 

 

responsibilities

 

 

• Review and revise integration test execution schedule, as required

 

 

Execute integration test

 

 

• Identify and document integration test discrepancies

 

 

• Resolve integration test discrepancies and document

 

 

• Identify required modifications (such as configuration

 

 

 

enhancements, interfaces, reports)

 

 

Re-execute integration tests

 

 

Update as required

 

 

Track test progress

 

 

Obtain test approval

 

 

• Summarize and communicate results to stakeholders

4. Deployment Production

 

 

Confirm Approach

Review with stakeholders and establish implementation locations

 

 

 

and configurations

 

 

Develop implementation approach

 

 

• Repeat appropriate tasks from development hardware and software

 

 

 

installation

Review and Update Deployment

Review existing documentation of results of tests

 

 

• Validate scope, objectives, and critical success factors

 

 

Update deployment approach

 

 

• Review and approve deployment

Implement Deployment

Review and reconcile system operations

 

 

• Review organization and system procedures

 

 

Promote to production

 

 

Update current operations

 

 

• Revise system release and deployment materials

 

 

Provide transition support

 

 

 

 

176 Portal Server 6 2005Q1 • Deployment Planning Guide

Page 176
Image 176
Sun Microsystems 2005Q1 manual Design Task List 6, Deployment Production