After installation

After installation

After installing the Tracker hardware, use the post-installation checklist (Table 4) to verify that all installation procedures were completed.

Table 4. Tracker controller post-installation checklist

Inspect shipment upon receipt

_____

Verify that the shipment is complete.

_____

Inspect the controller and accessories to verify that

 

there has been no shipping damage or loss.

_____

File a damage claim with the carrier, if necessary.

_____

Verify that the controller received is the one that

 

was ordered.

_____

Write down the controller model number for use

 

later.

Verify termination module mounting

_____

Verify that the controller is in a safe indoor

 

environment.

_____

Verify that the location enables appropriate

 

personnel to access the controller.

_____

Verify that the controller is mounted securely with

 

recommended fasteners and screws.

_____

Verify that the installation conforms to controller

 

dimensions, recommended clearances, and

 

viewing angles.

Verify 24 Vac power wiring

_____

Verify that the power wiring complies with

 

applicable codes.

_____

Verify the 24 Vac power connection to the

 

controller termination Block TB1.

_____

Check the power wiring for shorts and improper

 

grounds.

_____

If using conduit connections, make sure separate

 

conduits are used for power and communications.

_____

Inspect the controller printed circuit card for

 

damage.

Verify input and output wiring

_____

Verify that wiring complies with specifications.

_____

Inspect all binary and analog terminations at TB1.

Verify communication wiring

_____

Verify that wiring complies with specifications.

_____

Inspect communication wiring between devices.

_____

Verify that all connections are properly shielded.

Verify wire terminations with a voltmeter

_____ Verify that the tests detailed in Table 18 on page 70

provide acceptable values.

Verify main module installation

_____

Verify that the main module is snapped in tightly

 

against the termination module.

_____

Verify that there is LED5 (HRT) activity.

Verify display module installation

_____

Verify that the display module is snapped in tightly

 

against the main module.

_____

Verify that the touch screen illuminates when

 

touched.

Verify direct and modem communication wiring

_____

Verify that the recommended cable is used for a

 

direct PC connection.

_____

Verify that the recommended adapter is used for

 

the direct connection cable.

_____

Verify that the direct connection cable is connected

 

to the correct Tracker port.

_____

Verify that the phone cable is connected to the

 

correct Tracker port.

Verify Ethernet communication wiring

_____

Verify that the recommended cable is used for the

 

connection.

_____

Verify that the Ethernet connection cable is

 

connected to the correct Tracker port.

BMTK-SVN01D-EN

13

Page 21
Image 21