Before you Begin Installation - Planning

Before installation is started, several major factors must be considered to ensure that the installation process is as smooth and trouble free as possible, and that the final finished project meets the needs of the customers, users, audiences, and installer.

The installation consideration on the following pages, though not comprehensive, should be consulted to help ensure that key aspects have been considered.

1.Room layout

a.The room

The application diagram below shows a typical classroom installation.

PoleVault System

Typical classroom installation

Room factors to be considered should include, but are not confined to:

Room size, orientation, and layout:

Audience factors (e.g. number, ADA requirements, seating arrangements)

Existing installed furniture (bookcases, racks, cabinets, workbenches, sinks, etc.)

Windows, doors, and support pillar locations in relationship to the proposed screen location

Ceiling and wall type (important in assessing the installation hardware needed)

Ceiling type: dropped, spline, hard lid etc., structural type (wood, concrete, trusses), plenum or non-plenum

Wall type: drywall, cement, brick, etc.

WCheck the structural ceiling to ensure that it can handle a load four times the weight of the final setup.

PoleVault Systems Installation • Introduction — Planning

1-3

Image 5
Contents PoleVault Systems Installation Guide Safety Instructions English Precautions Consignes de Sécurité Français Sicherheitsanleitungen DeutschFCC Class B Notice PoleVault Systems Installation IntroductionIntroduction Introduction, contd PoleVault System installation and wiring overviewPoleVault Systems Installation Introduction Planning Typical classroom installationRoom layout RoomIntroduction Planning, cont’d Example classroom installationLocation of the screen and projector ADA overhead and side clearance requirementsLocation of MediaLink Controller and Wall Plates Example classroom with four speaker installationLocation of source devices Cabling obstaclesIncluded items Introduction Inventory OverviewInventory PoleVault System Devices and Hardware, cont’d Items not included Optional installation hardwareIntroduction Inventory Overview, cont’d Installation tools PoleVault Systems Installation Installation Installation OverviewOutline of installation steps PoleVault Systems Installation Installation Stage Stage One Install the Screen and ProjectorPCM 340 Projector Drop Ceiling Mount Slotted Pipe Supplied with PCMInstall projector to verify location Installation Stage One, cont’dMark screen location 1a Mark the screen locationVerify the image location 2f Slide and lock the projector onto the adjuster plate2e Attach the bracket to the projector Horizontal offset5a Mark structural ceiling for lag eye bolt installation Preliminary safety hardware installationCut the ceiling tile 4b Take measurements with the PCM 340 on the T-frameSecure the Projector Drop Ceiling Mount to the ceiling Finish Projector Drop Ceiling Mount installation7a Attach turnbuckles at the corners 7c Hand tighten the turnbuckles8a Install Raco box and plaster ring Install the electrical box if requiredInstall the Screen MLC 104 IP Plus MediaLink Controller Stage Two Install the Wall Plates and MLC 104 IP PlusThis stage involves installing the devices shown below Cables Installation Stage Two, cont’dIR/RS-232 communications cable control cable RS-232 or to an IR emitter1d Features for mud ring installation Install the mud ringsMLC 104 IP Plus mud ring 1c Insert the mud ring2c Pull the cables at each location Signal Cable Label colorPull the cables at the input locations MLC 104 IP Plus controller Install wall plates4a Connecting the MLC to the switcher Install MediaLink ControllerWire stripping lengths Connect the MLC to the projector with 4c Connect to the LAN using a CAT 5 cableAn RS-232 cable or IR emitter cable, as Appropriate4e Secure the MLC 104 IP Plus to the mud ring Connections made to the MLC 104 IP PlusFF 120 Flat Field Ceiling Speakers Stage Three Install the FF 120 Ceiling SpeakersInstall the speaker on the drop ceiling Installation Stage Three, cont’d2h Attach safety cable Cut ceiling tilePole captive screw connector Terminate the speaker cable for the PVS switcherStereo or dual mono output using parallel speaker wiring To terminate the cable, strip the end of the cable 0.2 inchThis stage covers installing the devices shown below Stage Four Install the PMK 550 and the PVS 305SAPVS 305SA PoleVault Switcher PMK 550 Pole Mount KitPoleVault Systems Installation Installation Stage 4 Install the PMK 550 base platePull the cables at the switcher location Installation Stage Four, cont’dSwitcher and projector cable overview 2b Gather the cables, pass them down the pipeBControl/power cable from the MLC 104 IP Plus Finish installing the Pole Mount kit4a Connect the cables to the switcher Connect the cables as follows to the PVS 305SA4d Cable the projector 4b Reattach UPB bracket and 4c projectorGlobal configurator software Stage Five Configure the Switcher and the SystemConfigure the switcher MLS Switcher Configuration program Configure the system Global Configurator Installation Stage Five, cont’dTest the system Loosen all pivot screws and adjust the vertical angle3c Check that an image is present, adjust as needed Adjust the configuration as necessary Final installationWhere installed, if necessary, adjust the sensitivity 3d Test the MLC configurationAlign the arrows on the housing rim and the dome tab Optional Accessory Installation VoiceLift SystemAttach the Z bracket to the ceiling tile and the back plate Plug VoiceLift cable into PVS 305SAOpen the sensor and loop a wire around the sensor Optional Accessory Installation Priority Page Sensor KitPriority Page Sensor Kit included parts UL-compliant junction box and cover4 Sensitivity knob adjustment Testing and Adjustment ProcedureTypical paging system with the PVS 305SA switcher Reference Information PoleVault Systems Installation Reference InformationLbs 0.1 kg Wall or furniture mountable with included Decora wall plateExtron PCM Reference Information, cont’dPVS 305SA specific symbol definitions SIS CommandsSIS Command/Response Table Ascii Telnet PoleVault Systems Installation Basic SIS CommandsExtron USA West