Step 3. Installing the Vent System

!

WARNING: YOU MUST NOT MIX DVP-SERIES

A. Vent System Approvals

 

AND SL D-SERIES COMPONENTS IN ANY VENT

 

 

SYSTEM CONFIGURATION.

These models have vent starting collars on both the top

 

 

 

and the back of the unit. Depending upon the installation,

Identifying Vent Components

decide which ONE set of starting collars will be used to

Approved vent system components are labeled for identifi-

attach the vent system. The starting collar sealing cap must

cation. NO OTHER VENTING SYSTEMS OR COMPO-

remain on the starting collar NOT used.

NENTS MAY BE USED. Detailed installation instructions

These models use SL-D-series, direct vent components

are included with each vent termination kit and should be

used in conjunction with this Installers Guide. Figure 8

when using the TOP vent collars. This pipe is tested and

shows vent system components and terminations.

listed as an approved component of the appliance. The pipe

The vent systems installed on this gas appliance may in-

is tested to be run inside an enclosed wall. There is no

clude one, two, or three 90° elbow assemblies. The rela-

requirement for inspection openings at each joint within the

tionships of vertical rise to horizontal run in vent configura-

wall. There is no required pitch for horizontal vent runs.

tions using 90° elbows MUST BE strictly adhered to. The

 

 

rise to run relationships are shown in the venting drawings

These models also use DVP-series direct vent components

and tables. Refer to the diagrams on the next several pages.

 

 

when using the REAR vent collars.

 

NOTE: Two 45° elbows may be used in place of one

 

 

The flame and ember appearance may vary based on the

90° elbow. Maximum and minimum rise to run ratios

must always be maintained in the vent system when

type of fuel burned and the venting configuration used.

using 45° elbows.

Vent System Termination Kits

 

 

Vent System Components

 

VERTICAL

DVP-SERIES

 

 

TERMINATION

DVP-TVHW

 

 

STORM COLLAR

 

 

 

 

 

 

ROOF FLASHING

DVP-TRAP

HORIZONTAL

 

HORIZONTAL PIPE

 

 

 

TERMINATION

 

 

 

SUPPORT (SL-Series)

 

 

 

 

WALL

 

 

DVP-TB1

FIRESTOP

 

 

(Required to have a minimum of 3 feet of vertical in the vent system)

PVK-80

For use with DVP venting. No adapters.

PIPE LENGTH

90 DEGREE

CEILING

WALL BRACKET

ELBOW

(SL-Series)

FIRESTOP

 

 

SL D-SERIES

*

SLK-SNKD

(There MUST be a 25% reduction in total H when using the snorkel cap except when using the simple up and out installation (see Fig. 9)

SLK-01TRD SLK-991DA

SLK-01TRF*SLFLEX2-01TRFA

* For use with flex vent only.

Figure 8. Vent System Components and Termination Kits

22

Heat & Glo • SL-350TRS-C, SL-550/750TRS-IPI-D2065-985 Rev. J • 5/06

Image 22
Contents Installation and Operation SL-750TRS-IPI-D SL-550TRS-IPI-D SL-350TRS-CSafety and Warning Information Table of Contents Log Set Assembly SL-350TRS-CNG, LP Service Parts List SL-350TRS-CValve Assembly Standing Pilot IgnitionSL-550TRS-IPI-D SL-550TRS-IPI-D Log Set Assembly Part number list on followingSL-750TRS-IPI-D Service Parts SL-750TRS-IPI-D, SL-550TRS-IPI-D Intermittent Pilot Ignition Valve AssemblyAppliance Certification High Altitude InstallationsInstallation Codes CertificationVent Directly BELOW. Keep Clear of ALL OB- Structions Requirements for the Commonwealth of MassachusettsManufacturer Requirements Introducing the Heat & Glo Gas Appliances Pre-install PreparationANY Such Action MAY Possibly Cause a Fire Hazard Diagram of the SL-750TRS-IPI-D GAS Line Electrical Access Access Diagram of the SL-350TRS-CLocating the Appliance Constructing the Appliance ChaseClearance Requirements Framing Dimensions Framing the Appliance34.93mm AT Each Joint 47 3/4 Identifying Vent Components Installing the Vent SystemSystem Configuration SL D-SERIES Components in ANY VentStraight UP Vertical Venting Flex VentWith TWO 900 Elbows Use DVP-Series Components only Venting with One 90 Elbow Use SL D-Series components onlyVenting with Two 90 Elbows Venting with TWO 2 90 o Elbows MAX. = 16 FT 4.8m + V 1 + H MAX. = 40 FT 12.2m Venting with Three 90 elbows Venting with Three 3 90 o Elbows + H 1 MAX. = 16 FT 4.8m + V 1 + H + H MAX. = 40 FT 12.2m Venting with Four 90 elbows Go to Install Firestops DVP Series Venting OnlySL-D and SL-Flex Series Venting Only Attach the First Vent Component to the Starting CollarsDVP, SL-D and SL-Flex Series Venting Hole and Vent PipeFor DVP Venting Only Vent TerminationSL-Series Venting Only For All VentingAlcove Applications Vent Termination Minimum ClearancesMinimum Height from Roof to Lowest Discharge Opening Standing Pilot Ignition System Positioning, Leveling, and Securing the ApplianceGas Control Systems Millivolt SystemGas Pressure Requirements Gas Supply LinePressure Natural Gas Propane Optional Accessories Wiring the ApplianceFor Standing Pilot Ignition Wiring Appliance Requirements Wall SwitchOperation using Battery Power Intermittent Pilot Ignition IPI Wiring DiagramFinishing NERGlass Specifications Installing the TrimShutter Settings Positioning the LogsBefore Lighting the Appliance After the InstallationDouble-check for faulty components Lighting the ApplianceAppliance Maintenance Important Turn OFF the GAS Before Servicing Your Appliance