For Vertical Terminations - To locate the vent and install the vent sections:

Locate and mark the vent centerpoint on the underside of the roof, and drive a nail through the centerpoint.

Make the outline of the roof hole around the centerpoint nail.

The size of the roof hole framing dimensions depend on the pitch of the roof. There MUST BE a 1-inch (25.4mm) clear- ance from the vertical vent pipe to combustible materials.

Mark the roof hole accordingly.

Cover the opening of the installed vent pipes.

Cut and frame the roof hole.

Use framing lumber the same size as the roof rafters and install the frame securely. Flashing anchored to the frame must withstand heavy winds.

Continue to install concentric vent sections up through the roof hole and up past the roof line until you reach the appropriate distance above the roof.

!WARNING: MAJOR U.S. BUILDING CODES SPECIFY MINIMUM CHIMNEY AND/OR

VENT HEIGHT ABOVE THE ROOF TOP. THESE MIN- IMUM HEIGHTS ARE NECESSARY IN THE INTER- EST OF SAFETY. SEE THE FOLLOWING DIAGRAM FOR MINIMUM HEIGHTS, PROVIDED THE TERMI- NATION CAP IS AT LEAST TWO (2) FEET (20 INCH-

ES FOR DVP PIPE) FROM A VERTICAL WALL AND 2-FEET BELOW A HORIZONTAL OVERHANG.

NOTE: This also pertains to vertical vent systems in- stalled on the outside of the building.

To seal the roof hole, and to divert rain and snow from the vent system:

Attach a flashing to the roof using nails, and use a non- hardening mastic around the edges of the flashing base where it meets the roof.

Attach a storm collar over the flashing joint to form a water-tight seal. Place non-hardening mastic around the joint, between the storm collar and the vertical pipe.

Slide the termination cap over the end of the vent pipe and rotate the pipe clockwise 1/4 turn.

 

 

HORIZONTAL

 

 

OVERHANG

2 FT.

2 FT. MIN.

 

20” MIN.

 

MIN.

VERTICAL

 

(DVP PIPE)

 

 

WALL

 

LOWEST

 

 

DISCHARGE

 

TERMINATION

OPENING

 

CAP

 

 

X

12

ROOF PITCH

IS X/ 12

H (MIN.) - MINIMUM HEIGHT FROM ROOF

TO LOWEST DISCHARGE OPENING

Roof Pitch

H (min.) ft.

flat to 6/12

1.0

over 6/12 to 7/12

1.25

over 7/12 to 8/12

1.5

over 8/12 to 9/12

2.0

over 9/12 to 10/12

2.5

over 10/12 to 11/12

3.25

over 11/12 to 12/12

4.0

over 12/12 to 14/12

5.0

over 14/12 to 16/12

6.0

over 16/12 to 18/12

7.0

over 18/12 to 20/12

7.5

over 20/12 to 21/12

8.0

Figure 31. Minimum Height from Roof to Lowest Discharge Opening

Heat & Glo • SL-350TRS-C, SL-550/750TRS-IPI-D2065-985 Rev. J • 5/06

37

Image 37
Contents SL-750TRS-IPI-D SL-550TRS-IPI-D SL-350TRS-C Installation and OperationSafety and Warning Information Table of Contents SL-350TRS-C Log Set AssemblySL-350TRS-C NG, LP Service Parts ListStanding Pilot Ignition Valve AssemblySL-550TRS-IPI-D SL-550TRS-IPI-D Part number list on following Log Set AssemblySL-750TRS-IPI-D Intermittent Pilot Ignition Valve Assembly Service Parts SL-750TRS-IPI-D, SL-550TRS-IPI-DInstallation Codes High Altitude InstallationsAppliance Certification CertificationVent Directly BELOW. Keep Clear of ALL OB- Structions Requirements for the Commonwealth of MassachusettsManufacturer Requirements Introducing the Heat & Glo Gas Appliances Pre-install PreparationANY Such Action MAY Possibly Cause a Fire Hazard Diagram of the SL-750TRS-IPI-D GAS Line Electrical Access Diagram of the SL-350TRS-C AccessLocating the Appliance Constructing the Appliance ChaseClearance Requirements Framing the Appliance Framing Dimensions34.93mm AT Each Joint 47 3/4 System Configuration Installing the Vent SystemIdentifying Vent Components SL D-SERIES Components in ANY VentStraight UP Vertical Venting Flex VentWith TWO 900 Elbows Venting with One 90 Elbow Use SL D-Series components only Use DVP-Series Components onlyVenting with Two 90 Elbows Venting with TWO 2 90 o Elbows MAX. = 16 FT 4.8m + V 1 + H MAX. = 40 FT 12.2m Venting with Three 90 elbows Venting with Three 3 90 o Elbows + H 1 MAX. = 16 FT 4.8m + V 1 + H + H MAX. = 40 FT 12.2m Venting with Four 90 elbows DVP Series Venting Only Go to Install FirestopsAttach the First Vent Component to the Starting Collars SL-D and SL-Flex Series Venting OnlyHole and Vent Pipe DVP, SL-D and SL-Flex Series VentingSL-Series Venting Only Vent TerminationFor DVP Venting Only For All VentingVent Termination Minimum Clearances Alcove ApplicationsMinimum Height from Roof to Lowest Discharge Opening Gas Control Systems Positioning, Leveling, and Securing the ApplianceStanding Pilot Ignition System Millivolt SystemGas Pressure Requirements Gas Supply LinePressure Natural Gas Propane For Standing Pilot Ignition Wiring Appliance Requirements Wiring the ApplianceOptional Accessories Wall SwitchIntermittent Pilot Ignition IPI Wiring Diagram Operation using Battery PowerNER FinishingShutter Settings Installing the TrimGlass Specifications Positioning the LogsDouble-check for faulty components After the InstallationBefore Lighting the Appliance Lighting the ApplianceImportant Turn OFF the GAS Before Servicing Your Appliance Appliance Maintenance