Carrier 58HDV installation instructions All Models Vent through Right-Side See Fig, Pvc

Page 20

Plastic Cap

Yellow or black

On Some Models

ONLY

INLET

Dual Pressure Switch

58HDV

Vent Drain

& Clamps

Drain Tube

Corrugated

5/8(15.9mm) ID &

Clamps

VENT

IN

ON

 

OFF

AIR FLOW

Relief Tube

Black Rubber

3/16″ 〈4.8mm) ID

2(50.8mm)

 

PVC

 

Coupling

EXHAUST

 

Either: The PVC Drain Tee or a field supplied 2(50.8mm) PVC Tee

Single Pressure Switch Details

Tee Trap White PVC (loose parts bag)

Elbow Tubes (2) Black Rubber 1/2(12.7mm) ID & Clamps (loose parts bag)

SIDE VIEW

Rotate downward 5° to 10°

Barbed Coupling, 1/2(12.7mm) OD (loose parts bag)

Drain Line Vent Tee 3/4(18.1mm) PVC or 1/2

(12.7mm) CPVC (Field sup- plied)

Drain Connector Black PVC 3/4(19.1mm) PVC X 1/2

(12.7mm) CPVC (Loose parts bag)

NOTE: Built--in channel will be angled 5° to 10° also.

Casing Grommet

 

Black Rubber 5/ (15.9mm) CPVC

8

 

(Loose parts bag)

25--24--68

A07708

Fig. 13 - All Models Vent Through Right Side

All Models Vent through Right-Side (See Fig. 13)

Disconnect the black drain tube between the drain vent and the trap. Rotate the inducer 180° for a right side vent after loosening the four

(4)inducer attachment screws. Reinstall and retighten the inducer screws to 20 in. lb. (2.3Nm) torque.

Using the 1/2(12.7mm) OD barbed coupling in the loose parts bag connect together with the two short 1/2(12.7mm) ID elbow tubes and connect the lower discharge port of the vent drain to the trap. Secure all connections with clamps.

Install the vent pipe grommet into the casing

Cut an appropriate length of 2(50.8mm) PVC pipe long enough to exit the cabinet and connect the vent drain to either:

SA 2(50.8mm) PVC coupling fastened onto the drain tee

Install tee trap into bottom section of tee.

Remove knockout from the side of the furnace casing where drain tube will exit.

Install casing grommet black rubber [5/8(15.9mm) ID grommet - in loose parts bag]

Install the 1/2(12.7mm) CPVC street elbow on discharge of trap.

Install the black PVC tube connector [3/4(19.1mm) PVC x 1/2(12.7mm) CPVC from loose parts bag] as shown in the illustration above.

Cut the black drain tube [5/8(15.9mm) ID - in loose parts bag] to length to fit between trap and tube connector through grommet.

Clamp both ends of the drain tube using clamps provided.

Glue the CPVC street elbow to the trap using appropriate cleaner and solvent cement.

Connect the tee trap and the main drain line exiting the casing as shown in Fig. 13

NOTE: It is recommended that all PVC piping and fitting connections be fit up and inspected before final cementing. Both the internal trap and the external tee trap must be primed before operation. Verify all condensate drain connections are securely clamped. A coupling and clamps (in loose part bag) may be installed as shown for future servicing of the vent system.

20

Image 20
Contents Installation Instructions Required Notice for Massachusetts Installations FIRE, EXPLOSION, and Asphyxiation Hazard Furnace Reliability HazardCUT Hazard Water Damage to Property Hazard Frozen Water Pipe HazardWinter Shutdown Installation Positions Installation RequirementsLocation and Clearances Carbon Monoxide Poisoning HazardFurnace Installation Considerations Horizontal Furnace InstallationCondensate Trap and Drain Lines LevelingDimensions and Clearances Outdoor Combustion Air Method Air Openings and Connecting DuctsKnock Outs Confined Space Installation RequirementsIndoor Combustion Air Unconfined Space Make the Following Check Ventilation AirVenting and Combustion Air Check Contaminated Combustion Air For Two Pipe Installation Direct VentDual Certified Direct or Non- Direct Vent Combustion Air and Vent Piping Insulation Guidelines Sizing Combustion Air and Vent PipeVent Termination Clearances Single Piping onlyDirect Vent Termination Clearance Other than Direct Vent Termination Clearance Condensate Drain Trap Frozen and Burst Water Pipe HazardUpflow Installations Top Vent See Fig OnlyUpflow Installations Vent through Left-Side See Fig Side ViewAll Models Vent through Right-Side See Fig PVCDownflow Left-Side Vent and Trap See Fig ExhaustDownflow Right-Side Vent and Trap See Fig Downflow Right-Side Vent and TrapHorizontal Left through Top See Fig ExhaustHorizontal Left-Side Vent See Fig InletHorizontal Right through Top See Fig Horizontal Right through TopHorizontal Right-Side Vent See Fig ExhaustVent Pipe Connection Connecting Vent and Combustion Air PipingCombustion Air Pipe Connection Direct Vent Horizontal Termination Connecting Vent Pipes and TerminationJoining Pipe and Fittings Using Exterior Risers Vertical TerminationVent Termination Shielding Multi Vent Termination ClearancesConcentric Vent and Combustion-Air Carbon Monoxide POISONING, Fire and Explosion Hazard Concentric Vent TerminationVertical & Horizontal Termination 40,000, 50,000, 60,000, & 75,000 Btuh Furnaces Gas Piping Requirements Gas Supply RequirementsFire and Explosion Hazard Fire HazardElectrical Operation Hazard Typical Gas Piping for UpflowHigh Altitude Air Pressure Switch Propane ConversionGeneral Derating Rules Additional Propane Connection RequirementsChanging Orifices for High Altitude Electrical SHOCK, Fire or Explosion HazardPower Supply Wiring Final Gas Piping CheckJunction Box J- Box Relocation Thermostat HeatingCooling Optional EquipmentFurnace Control Fuse Tap Select Interface BoardInstallation ConnectionsSizing InsulationAddition Of Air Conditioning Filter Installation using Filter RackFilters Combustible Floor Installation Subbase for Combustible FloorGas Supply Pressure Manifold Gas Pressure AdjustmentsStartup Main Burner Flame Check Temperature Rise CheckNatural Gas Input Rating Check Blower Adjustments Continuous- Fan using GHard Wired Continuous Fan Operation Changing Blower SpeedOn = OFF = Continuous Circulating Fan G Request Low Cooling Y1 RequestHigh Cooling Y1 & Y/Y2 or Y/Y2 Request Furnace Control Board Diagnostic Codes See Fig Heating Request with Gas Shut OffWiring Diagram Thermostat Wiring Guide No Connection SINGLE-STAGE Thermostat TWO-STAGE Catalog No 58HDV---01SI