Carrier 58HDV installation instructions Downflow Right-Side Vent and Trap See Fig

Page 22

58HDV

Plastic Cap

Yellow or black

Vent Drain

& Clamps

SIDE VIEW

Rotate downward 5° to 10°

NOTE: Built--in channel will be angled 5° to 10° also.

Single Pressure Switch Detail

AIR

FLOW

Elbow Tube Black Rubber 1/2(13 mm) ID & Clamps (Loose Parts Bag)

Barbed Coupling 1/2(13 mm) OD (Loose Parts Bag)

Dual Pressure Switch

 

 

AIR

 

 

FLOW

Drain Tube Corrugated

 

Black, 5/8(16 mm)

 

Drain Connector Black

ID & Clamps

OFF

PVC 3/4(19 mm)

ON

 

PVC X 1/2(13 mm)

 

 

CPVC (Loose parts bag)

Trap Connection

“Clamp ears” Pointed OUT

Relief Tube

Preassemble &

Black Rubber

insert into furnace

3/ (5 mm) ID

 

16

Coupling & Clamps

 

(Optional)

Drain Hose

 

Black Rubber

 

1/ (13 mm) ID Cut to

2

 

Fit & Clamps

 

On Some

2(51 mm) PVC Coupling

Models

 

ONLY

 

INLET

Either: The PVC

 

 

Drain Tee or a field

 

supplied 2(51 mm) PVC Tee

 

Tee Trap White PVC

 

(loose parts bag)

WARNING

 

Move Caps to

top of trap

 

 

Drain Tube Black Rubber,

 

5/ ID (16 mm) Cut to fit & Clamps

 

8

 

(loose parts bag)

A07768

Fig. 15 - Downflow Right-Side Vent and Trap

Downflow Right-Side Vent and Trap (See Fig. 15)

Remove the drain tee if installed.

Disconnect the hoses from the trap assembly, and remove trap and trap mounting bracket from the blower compartment. Using cover plate and gasket provided in the loose parts bag, cover the hole from the burner compartment to the blower compartment and secure with screws.

Move the caps to the top of the trap and mount the trap externally to the right side of the unit using the two(2) screws provided.

Connect the corrugated drain tube from the transition box to the trap as shown. If an extension is required, use the black PVC tube connector and the black 5/8(15.9mm) ID drain tube in the loose parts bag. Cut tube to length. Secure all connections with clamps.

Connect the drain hose from the Vent Drain to the trap. If an extension is required, use the black 1/2(12.7mm) OD barbed coupling, connect a black 1/2(12.7mm) ID elbow tube and a suitable section of a 1/2(12.7mm) ID drain tube to make connection from the vent drain to the trap. Secure all connections with clamps.

Install the vent pipe grommet into the casing

Cut an appropriate length of 2(50.8mm) PVC pipe long , enough to exit the cabinet and connect the vent drain to either:

SA 2(50.8mm) PVC coupling fastened onto the drain tee Install tee trap into bottom section of tee and glue pipe.

Remove knockout from the side of the furnace casing where drain tube will exit.

Connect the tee trap and the main drain line exiting the casing as shown in Fig. 15.

NOTE: Note: It is recommended that all PVC piping and fitting connections be fit up and inspected before final cementing. Both the external trap and the external tee trap must be primed before operation. Verify all condensate drain connections are securely clamped. A coupling and clamps (in loose part bag) may be installed as shown for future servicing of the vent system.

22

Image 22
Contents Installation Instructions Required Notice for Massachusetts Installations CUT Hazard Furnace Reliability HazardFIRE, EXPLOSION, and Asphyxiation Hazard Winter Shutdown Frozen Water Pipe HazardWater Damage to Property Hazard Location and Clearances Installation PositionsInstallation Requirements Carbon Monoxide Poisoning HazardCondensate Trap and Drain Lines Furnace Installation ConsiderationsHorizontal Furnace Installation LevelingDimensions and Clearances Knock Outs Air Openings and Connecting DuctsOutdoor Combustion Air Method Confined Space Installation RequirementsIndoor Combustion Air Unconfined Space Venting and Combustion Air Check Ventilation AirMake the Following Check Dual Certified Direct or Non- Direct Vent For Two Pipe Installation Direct VentContaminated Combustion Air Combustion Air and Vent Piping Insulation Guidelines Sizing Combustion Air and Vent PipeVent Termination Clearances Single Piping onlyDirect Vent Termination Clearance Other than Direct Vent Termination Clearance Condensate Drain Trap Frozen and Burst Water Pipe HazardUpflow Installations Top Vent See Fig OnlyUpflow Installations Vent through Left-Side See Fig Side ViewAll Models Vent through Right-Side See Fig PVCDownflow Left-Side Vent and Trap See Fig ExhaustDownflow Right-Side Vent and Trap See Fig Downflow Right-Side Vent and TrapHorizontal Left through Top See Fig ExhaustHorizontal Left-Side Vent See Fig InletHorizontal Right through Top See Fig Horizontal Right through TopHorizontal Right-Side Vent See Fig ExhaustCombustion Air Pipe Connection Direct Vent Connecting Vent and Combustion Air PipingVent Pipe Connection Joining Pipe and Fittings Connecting Vent Pipes and TerminationHorizontal Termination Vent Termination Shielding Using Exterior RisersVertical Termination Multi Vent Termination ClearancesConcentric Vent and Combustion-Air Vertical & Horizontal Termination Concentric Vent TerminationCarbon Monoxide POISONING, Fire and Explosion Hazard 40,000, 50,000, 60,000, & 75,000 Btuh Furnaces Fire and Explosion Hazard Gas Piping RequirementsGas Supply Requirements Fire HazardElectrical Operation Hazard Typical Gas Piping for UpflowGeneral Derating Rules High Altitude Air Pressure SwitchPropane Conversion Additional Propane Connection RequirementsChanging Orifices for High Altitude Electrical SHOCK, Fire or Explosion HazardJunction Box J- Box Relocation Power Supply WiringFinal Gas Piping Check Thermostat HeatingFurnace Control Fuse CoolingOptional Equipment Tap Select Interface BoardSizing InstallationConnections InsulationFilters Filter Installation using Filter RackAddition Of Air Conditioning Combustible Floor Installation Subbase for Combustible FloorStartup Manifold Gas Pressure AdjustmentsGas Supply Pressure Natural Gas Input Rating Check Temperature Rise CheckMain Burner Flame Check Hard Wired Continuous Fan Operation Blower AdjustmentsContinuous- Fan using G Changing Blower SpeedOn = OFF = High Cooling Y1 & Y/Y2 or Y/Y2 Request Low Cooling Y1 RequestContinuous Circulating Fan G Request Furnace Control Board Diagnostic Codes See Fig Heating Request with Gas Shut OffWiring Diagram Thermostat Wiring Guide No Connection SINGLE-STAGE Thermostat TWO-STAGE Catalog No 58HDV---01SI